Reference no: EM13859257
Process costing:
LSW Co. uses a process costing system to account for manufacturing costs. The following data pertains to the period just ended:
|
Direct Material Costs
|
Conversion Costs |
Beg. Inv.
|
$5,000
|
$3,000
|
Current
|
|
|
Production
|
96,000
|
58,000
|
The beginning inventory consisted of 2,500 units of partially complete products that were 80% complete in material costs and 75% complete in conversion costs. Production on 48,000 units was begun during the period, and of those, 3,000 were incomplete at the end of the period. Those units in ending inventory were 30% complete in material costs and 40% complete in conversion costs.
Required:
Using Excel or some other spreadsheet software, you need to develop an automatic process costing system based on the FIFO method that will calculate LSW's ending inventory and cost of goods manufactured for every period. To do this, you will need to label a tab on a spreadsheet "INPUT." On this sheet, the inputs that change every period will be entered. IMPORTANT: the input sheet has data points only. No calculations of any sort should be on the input sheet. For example, the number of products started, the number of units in ending inventory, the percentage of completion with respect to materials, the material costs in beginning inventory are all examples of data points. You then need to label another tab "Cost of Production Report" or "OUTPUT." On this tab, you will perform all calculations for the current period by linking the data from the INPUT tab. In this manner, for every subsequent period, one would only have to update the information under the INPUT tab and the OUTPUT sheet would automatically calculate the correct EI balance and Cost of Goods Manufactured (HINT: there should not be any "hard" numbers on the OUTPUT sheet).
Standard Costing:
ACTUAL RESULTS
|
|
Total overhead costs
|
$483,500
|
Variable overhead costs
|
$185,000
|
Fixed overhead costs incurred
|
$298,500
|
Number of products produced
|
11,900 units
|
Direct labor costs
|
$104,703 (10,265 hours @ $10.20)
|
Direct material costs
|
$599,841 (120,450 lbs. @$4.98/lb.)
|
STANDARDS
|
Per unit/DLH
|
Direct materials
|
10 pounds @ $5 per pound
|
Direct labor
|
1 DLH @ $10/DLH
|
Variable overhead rate
|
$15 per allowed DLH
|
Fixed overhead rate
|
$25 per allowed DLH
|
Total overhead rate
|
$40 per allowed DLH
|
Normal activity level
|
12,000 units
|
Fixed OverheadEstimate
|
$300,000
|
Required:
Using Excel or some other spreadsheet software, you need to develop an automatic standard costing system that will calculate JCL's variances for every period. To do this, you will need to label a tab on a spreadsheet "INPUT." On this sheet, the inputs that change every period will be entered. IMPORTANT: the input sheet has data points only. No calculations of any sort should be on the input sheet. For example, the actual production for the period, the actual per unit cost for materials, the actual labor hours for the period, the actual variable overhead costs are all examples of data points. This sheet would be accessed every period and updated as these inputs change.
You then need to label another tab "STANDARDS." On this tab, you will put all the standards JCL uses to gauge their performance as well as the expected level of activity. This sheet is accessed periodically as JCL re-visits and revises their standards. This would probably not happen every period.
You then need to label another tab "VARIANCES" or "OUTPUT." No hard numbers should go on this sheet. It should perform all variance calculations for the current period by linking the data from the INPUT tab and the STANDARDS tab. In this manner, for every subsequent period, one would only have to update the information under the INPUT tab (and, less frequently, the STANDARDS tab,) and the OUTPUT sheet would automatically calculate the variances.
Variable Costing:
March:
Beginning inventory= 2,500 units $26,500 ($10,000 variable)
Production= 32,000 units
Sales = 31,000 units @ $50 each
VMC (DM, DL, and VOH) = $129,600
FMC = $300,000
VS/A costs = $124,000
FS/A costs = $550,000
April:
Beginning inventory = ?
Production = 33,000 units
Sales = 34,000 units @ $50 each
VMC (DM, DL, and VOH) = $133,650
FMC = $300,000
VS/A costs = $126,000
FS/A costs = $550,000
Required:
Variable costing income and full-absorption costingincome for both March and April.Prepare automated reportsfor both income methods for both months. A proper solution will include a separate input section (under a separate tab) in which only data items will be entered (you may use one input tab for both months). In a separate section (under another tab), you should link items from the input tab to anoutput section that contains the income reports (you may use one section for both variable and full-absorption costing income). Using the information above, your solution will be for these periods.
Write a paper on the advantages of the inventory models
: Write a 300 to 500 word paper on the advantages and disadvantages of the three different inventory models known as EOQ (economic order quantity).
|
Case diagram-airline reservation problem
: To summarize, this swing GUI displays the reservation form and the airplane seating availability "diagram". Construct a Use-Case diagram for this airline reservation problem.
|
Find a current news article in the ashford university
: Find a current news article in the Ashford University Library's ProQuest Newsstand database about an ethical issue that involves computer technology, or involves a technology company Summarize the facts and major points from the article and be sure t..
|
Determine a frequency and severity rating
: The Pebbles, Inc. (the "Company) is a casino & resort operating company based in Las Vegas, Nevada, USA. The Company's resorts feature high-end accommodations, gaming and entertainment, convention and exhibition facilities, celebrity chef restaur..
|
Develop an automatic process costing system
: You need to develop an automatic process costing system based on the FIFO method that will calculate LSW's ending inventory and cost of goods manufactured for every period.
|
Draw an aon network for the construction activity
: Draw an AON network for the construction activity. What is the critical path? (note the path and the time)? Draw the Gantt chart for the whole construction activity
|
Seminar topic- service quality
: Seminar topic: Service Quality. View this week's archived Seminar and write a 1-page paper, double spaced, that summarizes the Seminar and what you learned
|
Estimate the values using the high-low method
: Estimate the values of a and b, using the High-Low Method, and the Linear Regression method.
|
Benefits of the specific product or brand you selected
: Think about the last purchase you made in each of the following product categories. Clearly describe the features, advantages, and benefits of the specific product or brand you selected
|