Develop an aggregate planning schedule for gobalcell

Assignment Help Supply Chain Management
Reference no: EM13759340

1. Aggregate Planning Model

GlobalCell is a cell phone producer in Europe, the demand for the first half of the coming year is forecasted in the table below.

Month

Demand in Unites

1

1000

2

1200

3

1000

4

1300

5

1500

6

1700

The plant operates for 20 days a month, eight hours each day. One worker can assemble a cell phone every 10 minutes. Workers are paid 20 euros per hour and a 50% premium for over time. The plant currently employs 1250 workers. Each cell phone costs 20 euros to make. The inventory carrying cost of a cell phone is 3 euros per phone per month. The company has no layoff policy in place. Overtime is limited to a maximum of 20 hours per month per worker. Assume that the company has a starting inventory of 5000 unites and wants to have the same level of inventory at the end of the schedule.

Develop an aggregate planning schedule for GobalCell for the next 6 months.

2. Inventory Management/Multi-item Joint Replenishment EOQ - Model

The Lamps Store sells 2 types of table lamps: classic and contemporary. The annual demand for the classic table lamp is 200 units while the annual demand for the contemporary table lamp is 300 units.

Assume each lamp costs Lamps Store $50 to purchase from its supplier, and the fixed ordering cost is $300 each time. For each type of table lamps ordered and delivered on the same truck, an additional fixed handling cost of $100 is charged. The company has a holding cost of 20 percent of the unit purchasing cost.

The Lamps Store decides to order 2 models of lamps at the same time using the same truck. What is the optimal lot size for each model?

3. Transportation Model

Frost Generators Co. operates factories in Cleveland, Bedford, and York. Production volumes over the next 3 months planning period for a particular generator is as follows

Factory

3-month production volume (units)

Cleveland

5000

Bedford

6000

York

2500

The company sells the generators through four regional warehouses in Boston, Chicago, St Louis, and Lexington. The 3-month demand of the warehouses is as follows

Warehouse

3-month demand forecast (units)

Boston

6000

Chicago

4000

St Louis

2000

Lexington

1500

The transportation cost per unit from factories to warehouses are given as follows

Factory to Warehouse

Boston

Chicago

St Louis

Lexington

Cleveland

3

2

7

6

Bedford

7

5

2

3

York

2

5

4

5

Management wants to use linear programming method to determine how much of its production units should be shipped from each factory to each warehouse such that the total transportation costs would be minimized.

1) What are the decision variables and definitions?

2) What is the objective function?

3) What are the constraints?

Reference no: EM13759340

Questions Cloud

Scheduling issues often cause more complexity on projects : Why do you think scheduling issues often cause more complexity on projects? Explain the following schedule development tools and concepts: Gantt charts, critical path method, PERT and critical chain scheduling. Discuss why many information technology..
Pathophysiology : The problem that underlies her diabetes is that her own body has destroyed the cells in her pancreas that produce insulin
The importance of the ten strategic points document : Assistance with the following assignment: Review the Unit VII Lesson regarding the Ten Strategic Points. Briefly write an introductory paragraph detailing the importance of the Ten Strategic Points Document. Refer back to the article(s) that were use..
Why is it important to keep the risk register up to date : Why is it important to keep the risk register up to date? Why is it important to document contract changes? Why should project teams be watchful for constructive change orders? What is involved in monitoring and controlling projects?
Develop an aggregate planning schedule for gobalcell : Develop an aggregate planning schedule for GobalCell for the next 6 months - what are the decision variables and definitions and what is the objective function - determine how much of its production units should be shipped from each factory to each ..
Describe the first nonliterary work of art : Describe the first nonliterary work of art. Your description should include: Media, form, or genre and Summary of the work.
Elements of organizational advocacy : Elements of Organizational AdvocacyRead How to Lead a Self-Managing Team. Analyze and summarize examples of each of the six elements of organizational advocacy and describe how each is important to the case.
Financial objective of maximizing shareholder wealth : The committee chairman has laid the groundwork for approving requests that managers of various organizational units have submitted by reminding the group that their charge is to approve the investment opportunities that will best meet the company'..
Top ten tips on managing diverse teams : In the article "Top Ten Tips On Managing Diverse Teams" Ten Tips On Leading A Diverse Team   the author, Simon Mitchell a Managing Director in the UK, defines ten ways to lead a successful "diverse" team. Joanne Sujansky in her article "The five bigg..

Reviews

Write a Review

Supply Chain Management Questions & Answers

  Supply chain network design for cwc

This assignment explain the supply chain management process of cwc. What is the current annual supply chain cost?

  Criteria when making new location decisions

Identify a number of the typical criteria used when making new location decisions

  Draw the project network

Determine the mean critical path for Brent's job search process. What is the variance of the project duration?

  Compare and contrast economic - market, and relevancy

Please compare and contrast economic, market, and relevancy value.

  Brushing up on inventory control

Health system in Pennsylvania

  Supply chain strategy

Supply chain strategy

  What is the economic order quantity for fans in units

Nittany Fans of Lewistown, Pennsylvania, is a distributor of industrial fans used in plants, warehouses, and other industrial facilities.

  What factors reduce the capacity of the organization

What factors reduce the capacity of the organization to get its objectives?

  What is the total annual cost

What is the total annual cost

  Supply chain management questions

Briefly define the following two supply chain metrics: (i) inventory turnover ratio and (ii) supply chain velocity.

  Explain the supply chain management concept

Explain the supply chain management concept, Differentiate between public and private sector organisations in terms of their supply chain objectives and strategies

  How warehouses can add value in the supply chain

How warehouses can add value in the supply chain

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd