Project Planning and Scheduling
Learning Outcome 1: Ability to develop project report using EVMS and communicate with project stakeholders
INSTRUCTION:
1. Project
2. Please develop a work program (refer to the attached excel - tasklist), generate plan target and update actual progress. Based on the work program answer and submit the project based on following questions.
QUESTIONS:
1. Setting for the project:
- File Name: Put Your Full Name as the File Name for Ms Project File
- Project Start Date: 1 January 2024 (Monday)
- Daily Schedule: 8 am - 7 pm (8 am - 12 pm, then 1 pm - 7 pm setting in calendar)
- Working Day: Every day (No holiday)
- Daily hours: 10 hours
- Weekly hours: 70 hours
- Day in Month: 30 Days
- Save File into folder name 1. Original
2. Generate Plan/Target Progress:
- Save Files into Folder Name 2. Plan
- Generate data (blue colour) for financial (actual cost) and physical progress (% complete) based on biweekly target cycle date as shown below.
- Save files based on the biweekly plan target date (green colour)
3. Update Actual Progress:
- Save files into folder name 3. Actual
- Files need to be save/set baseline first before updating/tracking.
- Generate data (yellow colour) for financial (actual cost) and physical progress (% complete) based on biweekly updated cycle date as shown below. You can also calculate the variance value (orange colour) once you got actual cost and % complete values.
- Please update based on three (3) dates only based on the given scenario:
o Info on 14/1/2024
• Survey & Setting Out at Zone A - Actual Start Date (1/1/2024), Actual Finish Date (11/1/2024)
• Earthwork at Zone A - Actual Start Date (12/1/2024), % complete 20%
• Survey & Setting Out at Zone B - Actual Start Date (12/1/2024), % complete 10%.
o Info on 28/1/2024
• Earthwork at Zone A - Actual Start Date (12/1/2024), Actual Finish Date (24/6/2023)
• Survey & Setting Out at Zone B - Actual Start Date (12/1/2024), Actual Finish Date (19/1/2024)
• Earthwork at Zone B - Actual Start Date (25/1/2024), % complete 5%
• Excavation footing at Zone A - Actual Start Date (25/1/2024), % complete 5%.
o Info on 11/2/2024
• Earthwork at Zone B - Actual Start Date (25/1/2024), Actual Finish Date (4/2/2024)
• Excavation footing at Zone A - Actual Start Date (25/1/2024), Actual Finish Date (5/2/2024)
• Lean Concrete at Zone A - Actual Start Date (6/2/2024), Actual Finish Date (7/2/2024)
• Formwork at Zone A - Actual Start Date (8/2/2024), % complete 18%
• Excavation footing at Zone B - Actual Start Date (5/2/2024), % complete 80%.
4. Draw Financial and Physical Progress Graph:
- Based on the updated financial and physical progress values as in item (3), please use excel software to draw the financial and physical progress graph that shows the 3 in 1 graph i.e., target, actual and variance values.
***Note:
- You are given 3 files (Excel Task list, Steps, Setting) to assist you in completing the exercise.