Develop a risk management plan for your project

Assignment Help Other Subject
Reference no: EM132353261

Undertake Project Work Assignment -

Assessment Task 1 - Define Project and Develop a Plan

Performance objective - Candidates will demonstrate knowledge and skills required to define projects and develop project plans.

Assessment description - Using the workplace scenario information provided, you will determine the scope of a project and develop a portfolio of draft planning documentation to discuss with your Operations General Manager (the assessor). You will then negotiate aspects of the project with your assigned project team. Finally, you will submit final planning documentation for approval.

Procedure -

1. Review the simulated business documentation, including policies and procedures, in the document 'Max Lionel Realty.docx'. Review templates contained in the document 'Project planning templates.docx' for possible use or adaptation in completing project requirements.

2. Review the scenario information provided in Appendix 1.

3. Receive details from Operations General Manager (the assessor) of your project team, cost, skills, and suggested project deliverables and timeframes.

4. Determine project scope. Develop appropriate initiation and scope documents for discussion with Operations General Manager (the assessor).

5. Determine additional documentation required to determine project and develop deliverables.

6. Define project stakeholders. Determine how you will engage and manage stakeholders to achieve project objectives. Develop communication and stakeholder management plans for discussion.

Note: Consider scenario information and organisational structure to determine stakeholders and stakeholder interests.

7. Identify personal responsibilities and reporting requirements.

8. Determine relationship of project to other projects, systems, business operations, strategic aims of organisation, and external legislative requirements.

9. Determine resources and access to resources. Consult with Operations General Manager (the assessor) to clarify if necessary.

10. Determine project management tools, such as software (e.g. Microsoft Word, MS Excel, and MS Project) and templates, etc.

Note: You may use software tools or use or adapt the templates provided.

11. Using an appropriate project management tool, develop your project plan (version 1). Include:

a. work breakdown structure: stages of development or of task completion (Design, Develop, Implement, Evaluate); opportunities for (peer and stakeholder) review and feedback; coordination of roles and sharing of responsibility for deliverables; dependencies

b. timelines

c. roles and responsibilities for each team member

d. resourcing requirements.

12. Develop a risk management plan for your project (version 1) for discussion. Include consideration of WHS risk management. Identify, assess and suggest treatment of at least three additional risks, including financial risk. Record risks on a risk register and complete a risk assessment document for each risk.

Note: You may use software tools or use or adapt the templates provided.

13. Develop a budget (version 1) for the project.

Note: You may use software tools or use or adapt the template provided.

14. Meet with Operations General Manager (the assessor) to discuss:

a. project scope

b. additional documentation required to determine project and develop deliverables.

c. project stakeholders

d. personal responsibilities

e. relationship of project to other projects, systems, strategic aims of organisation

f. resources and access to resources

g. portfolio of documents:

i. project initiation and scope documents

ii. project plan (version 1)

iii. risk management plan (version 1)

iv. budget (version 1).

15. Ask for feedback from your Operations General Manager (the assessor) on your version 1 drafts and ensure understanding of any additional project issues or changes to project parameters.

16. Meet with your project team to:

a. negotiate roles and responsibilities

b. Agree on version 2 of documents for approval by Operations General Manager (the assessor):

i. project plan (version 2)

ii. risk management plan (version 2)

iii. budget (version 2).

c. Incorporate Operations General Manager (the assessor) feedback into planning project:

Note: The meeting will be observed by your assessor. Follow your communication plan or agree to a time and date.

When meeting with your team, be:

i. professional

ii. accommodating and conscious of varying skill levels, interests, backgrounds

iii. submit documentation as per specifications below.

Specifications -

You must:

  • meet with Operations General Manager to discuss project scope and portfolio of planning documents
  • participate in project meeting/s with project team

Submit:

  • project initiation and scope documents, including: a project brief; a project scope; a stakeholder analysis; a communication plan; roles and responsibilities; project snapshot
  • a project plan (version 1 and version 2)
  • a risk management plan (risk register and risk assessment for each of four risks) (version 1 and version 2)
  • a budget (version 1 and version 2).

Your assessor will be looking for:

  • communication and negotiation skills to work with team members and other stakeholders to maintain project schedules
  • literacy skills to read, write and review a range of documentation
  • planning and organising skills to develop project plans
  • numeracy skills to analyse data and to compare timelines and implementation costs against budgets
  • culturally appropriate communication skills to relate to people from diverse backgrounds and people with diverse abilities
  • knowledge of relevant legislation from all levels of government that may affect aspects of business operations, such as: anti-discrimination legislation, ethical principles, codes of practice, privacy laws, environmental issues and WHS
  • knowledge of organisational structure and chains of authority and communication within the organisation
  • knowledge of how the project relates to the organisation's overall mission, goals, objectives and operations.

Assessment Task 2 - Administer and Monitor Project

Performance objective - Candidates will demonstrate knowledge and skills required to administer and monitor projects.

Assessment description - Using the workplace scenario information provided, you will work collaboratively with your project team to administer and monitor a project (initiated, planned and discussed in Assessment Task 1) in order to achieve the project deliverables.

Procedure -

1. Review the simulated business documentation, including policies and procedures in the document 'Max Lionel Realty.docx'. Review templates contained in the document 'Project planning templates.docx' for possible use or adaptation in completing project requirements.

2. Review the scenario information provided in Appendix 2.

3. Determine monitoring and record-keeping system requirements from scenario for project as planned.

4. Determine personal need for support.

5. Meet with the team to:

a. clarify roles and responsibilities and ensure written record of agreement, e.g. obtain signatures on roles and responsibilities template provided

b. determine need for support and inform team members of your support needs

c. discuss monitoring and record-keeping systems as required by the organisation

d. discuss risk processes for identifying risks and risk management approaches.

Note: Minutes of these meetings should be attached to your project status reports. You may need to meet on several occasions. Meetings may be observed by your assessor. Follow your communication plan or agree to a time and date.

6. Plan to support a team member. Arrange suitable time with team member and assessor (to observe). You may, for example, provide assistance with deliverables, coach, train, etc.

Note: Ensure you adhere to budgetary constraints and timelines. All resources and time spent on the project will count towards expenditure.

7. Meet with team member to provide support.

8. Complete the following personal roles and responsibilities:

a. implement monitoring and record-keeping, using or adapting the template provided

b. develop project deliverables

c. ensure quality assurance on draft deliverables as required by your project plan.

9. Undertake risk management as per your project plan. Provide risk management reports (may include change requests and/or issues logs). Use or adapt the templates provided.

Note: Your Operations General Manager (the assessor) will inform your project team of contingencies that you will need to manage. Coordinate actions with your project team members. Each team member will have at least one contingency to manage.

10. Submit documentation as per specifications below.

Specifications -

You must:

  • participate in project meeting/s
  • provide appropriate support to one team member

submit:

  • a written record of agreement with roles and responsibilities
  • three status reports as per record-keeping requirements
  • risk management reports: change requests and/or issues logs
  • draft project deliverables for quality assurance
  • final project deliverables.

Your assessor will be looking for:

  • communication and negotiation skills to work with team members and other stakeholders to maintain project schedules
  • literacy skills to read, write and review a range of documentation
  • planning and organising skills to monitor and maintain implementation schedules
  • numeracy skills to analyse data and compare timelines and implementation
  • culturally appropriate communication skills to relate to people from diverse backgrounds and people with diverse abilities
  • knowledge of relevant legislation from all levels of government that may affect aspects of business operations, such as: anti-discrimination legislation, ethical principles, codes of practice, privacy laws, environmental issues and WHS
  • knowledge of organisational structure and chains of authority and communication within the organisation
  • knowledge of how the project relates to the organisation's overall mission, goals, objectives and operations.

Assessment Task 3 - Finalise and Review Project

Performance objective - Candidates will demonstrate knowledge and skills required to finalise and review projects.

Assessment description - Following on from Assessment Tasks 1 and 2 and using the workplace scenario information provided, you will, drawing on consultation with your project team, complete financial record keeping, reassign staff to roles, complete project documentation for sign off and review project outcomes against project scope and plan. You will then produce a report on the project for stakeholders.

Procedure

1. Review the simulated business documentation, including policies and procedures, in the document 'Max Lionel Realty.docx'. Review templates contained in the document 'Project planning templates.docx' for possible use or adaptation in completing project requirements.

2. Review the scenario information provided in Appendix 3.

3. In consultation with your project team, complete financial record-keeping for the project:

a. compare budgeted spend with actual

b. produce a budget variation report.

Note: You may use or adapt the template provided. Meetings may be observed by your assessor. Follow your communication plan or agree to a time and date.

4. In consultation with your project team and management, assign project team members to roles. Obtain agreement on new roles and responsibilities. You may use or adapt the template provided (under initiation and scope) to record agreement on new role descriptions.

Note: Meetings may be observed by your assessor. Follow your communication plan or agree to a time and date.

5. Produce a handover report for the Project Sponsor (the assessor) for sign-off. You may use or adapt the template provided.

6. In consultation with your project team:

a. review the project's outcomes against objectives, including budgetary performance

b. review team processes

c. review the project management tools used, evaluate their contribution to the project and discuss possible alternatives

d. discuss lessons learned from implementation of the project.

Note: You may use or adapt the post-project review meeting agenda template provided. Meetings may be observed by your assessor. Follow your communication plan or agree to a time and date.

7. Produce a post-project review report for all stakeholders, including the Board of Directors, containing:

a. a review of project outcomes against objectives, including budgetary performance

b. a review of team processes

c. a review of the project management tools used, an evaluation of their contribution to the project and any recommendations for alternative tools for use in the future

d. a discussion of lessons learned from implementation of the project

e. recommendations for the implementation of future projects based on the lessons learned, ensuring your report takes account of specific organisational requirements, e.g. legislative requirements and strategic plans.

Note: You may use or adapt the post-project review report template provided.

8. Submit documentation as per specifications below.

Specifications -

You must: participate in project meeting/s

Submit:

  • budget variation report for sign-off
  • signed role descriptions for sign-off
  • handover report
  • post-project project review report.

Your assessor will be looking for:

  • communication and negotiation skills to work with team members and other stakeholders to maintain project schedules
  • literacy skills to read, write and review a range of documentation
  • planning and organising skills to develop, monitor and maintain implementation schedules
  • numeracy skills to analyse data and to compare timelines and promotional costs against budgets
  • culturally appropriate communication skills to relate to people from diverse backgrounds and people with diverse abilities
  • knowledge of relevant legislation from all levels of government that may affect aspects of business operations, such as: anti-discrimination legislation, ethical principles, codes of practice, privacy laws, environmental issues and WHS
  • knowledge of organisational structure, and lines of authority and communication within the organisation
  • knowledge of how the project relates to organisation's overall mission, goals, objectives and operations.

Attachment:- Undertake Project Work Assignment Files.rar

Reference no: EM132353261

Questions Cloud

Determine the optimal order quantity : A mail-order house uses 16,540 boxes a year. Carrying costs are 60 cents per box a year, and ordering costs are $96. The following price schedule applies.
Analyze social consequences of not leading with intelligence : Analyze some of the social and organizational consequences of not leading with intelligence (emotional, cultural, etc...) Defend at least three ways that.
Discuss your approach to minimize your impact on environment : Discuss your approach to minimize your impact on the environment. Discuss your approach to care about suppliers, customers, community, employees.
Identify power relations for aspects of positive sum outcome : Identify power relations for their aspects of positive-sum, zero-sum, or negative sum outcomes. Deconstruct in a systematic analysis the evolution of an actual.
Develop a risk management plan for your project : BSBPMG522 Undertake Project Work Assignment, Choice Business College, Australia. Develop a risk management plan for your project
Focus on the financial statement analysis : Last week you selected a publicly traded company and found their annual report. Focus on the financial statement analysis chapter you are reading this week.
What is your strategy to improve the areas identified : Review this week's assigned reading in the course text, Essential Guide to Critical Reading and Writing. Then, review and reflect on the journal entry you wrote
How will you diagnose organization and design components : Be sure to describe to describe the diagnostic plan. How will you diagnose the organization and the design components (chapter 4)? Describe how the external.
Describe benefits related to voluntary employee benefits : The video shares a discussion specifically on 9 benefits related to voluntary employee benefits. Review the VEB's and if you could only have 4 of them.

Reviews

len2353261

8/6/2019 9:42:39 PM

Submission details - The assessment task is due on the date specified by your assessor. Any variations to this arrangement must be approved in writing by your assessor. Submit this document with any required evidence attached. See specifications above for details.

Write a Review

Other Subject Questions & Answers

  Draft a notice of meeting and proxy form

Draft (create ) a notice of meeting and proxy form - the agenda is to amend the constitution to create a class of preference shares - read section 254a(2).

  What is an example of international criminal justice system

What is an example of international criminal justice system? What relevance is there to examining international justice systems?

  What way was tsunami more visible than these other disasters

Why is there typically lots of claimsmaking attention given to disasters that produce massive suffering in a short period of time (such as the tsunami or an airplane crash) but much less attention given to disasters that produce the same or more s..

  How that development can influence policy to solve problem

The author of chapter 1 discusses several developments that influence policy-making. Select one of the developments in chapter 1 and describe how that developme

  Provide practice assessments such as monthly

Many school systems now seem to "teach to the test" and provide practice assessments such as monthly's, quarterly's, or benchmarks based on six or nine weeks.

  Identify potential threats to internal and external validity

Identify the independent and dependent variables in this experiment. Identify what type of research design was used. Identify potential threats to internal and external validity in this experiment.

  Explain adults returning to college face

Double space the entire document and each document you submit in this class. Center the title.Do not use "you" in this essay or in any essay

  Review the information in the practicum project plan

Review the information in the Practicum Project Plan (PPP) Overview document introduced in Week 3. The overview describes the components that must be included in your plan

  Racial- and ethnic-minority and low-income

Analyze three factors that cause many racial- and ethnic-minority and low-income students to be identified as gifted underachievers. Explain your rationale for choosing these factors.

  Discuss appropriate economic predictors

PAD 520- Discuss the results of research, identifying models used to obtain the results. Provide available federal data. Discuss appropriate economic predictors. Propose at least three reliable, implementable recommendations.

  Operant conditioning and superstitions

Describe the principles/concepts which can be applied to explain the process by which operant conditioning can lead to the development and maintenance of superstitions.

  How ge is addressing the needs of their hospital customers

Visit GE Healthcare (www.gehealthcare.com/). In context to the major points of chapter 5, define how GE is addressing the needs of their hospital customers by the design of this Web site?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd