Reference no: EM132300443
Assignment - Group Project
Project Execution Plan
Assume that your team has been appointed as the Information Technology (IT) project planners for the project
PROJECT: DEVLEOPMENT OF A NEW INFORMATION TECHNOLOGY CENTRE
Introduction:
Your group has been appointed by a potential client to build a new Information Technology Centre in your capital city. The land owned by the client with an approved budget of $40 million only for the new IT Centre. In addition to the Centre, the client allocated additional fund of 25 million for the latest IT Technology support to cater for the IT needs for the next five years.
As the IT Project Manager of the project you are requested to submit a Project Execution Plan (PEP) for this development.
The group has to develop a project execution plan to manage the activities required to construct the IT Centre.
The tasks required include:
• Develop a scope of this project. This requires to develop the scope for the facilities and IT support independently
• Developing a budget for construction of the IT centre and ensuring that the owner can provide the funds and are committed to funding the project
• Obtaining planning permits and approvals from the relevant authorities.
• Design and construction of the IT Centre.
• Completion and handover.
Your team should produce a Project Execution Plan (PEP) which sets out how the project is to be executed. The project schedule forms part of the PEP document.
The Basis of Schedule which may form part of the PEP sets out the underlying assumptions going into the plan and how the plan is to be constructed, scheduling units, choice of calendars, choice of planning tool, etc. Will the schedule be resourced? Will the resources have costs associated with them? What will be the availability (calendar) of the various resources? That is, what are the work and non-work days (Public holidays, RDOs etc)?
All other assumptions must be stated clearly at the beginning of the report(s).
Stage 1 (Wk. 4) - Prepare project Charter
Prepare:
• Prepare Project Scope.
• List of assumptions used in the project (if any)
• Planning methodology - outline the technique for the delivery of the project.
• Use Template to prepare the full report on Project Charter
Stage 2 (Wk. 4-7) - WBS and Manual Scheduling
• Project calendar showing start and finish dates, weekends, RDO's, and public holidays, etc.
• Develop a Work Breakdown Structure (WBS), an Organisation Break Down Structure (OBS) and a Responsibility Assignment Matrix (RAM).
• List of tasks, durations and their logical relationship.
• Execution program (a manual PDM diagram or a Gantt chart).
• Estimate the cost of the project as per the WBS and listed activities.
• Develop a risk register using RBS as per WBS to identify and prioritize all risk associated with this project.
• Sub-contractors or consultants schedule for the project.
• References if any.
Stage 3 - Computerized Planning
Prepare the following by utilising a project management software application MS Project 2016:
• A list of tasks and work breakdown schedule for the project including activity durations
• A project Calendar
• A PDM diagram and a Gantt Chart
• A weekly Gantt Chart of all activities sorted by WBS
• A list and cost of all resources (own and/or subcontracted).
• Final cost and detail budget reports as per WBS
• Various resource schedules in the form of Gantt Charts
• A budget and cost forecast. Also, develop an "S" curve using the software
• Other relevant reports to support the PEP
Provide a final report (Stage 1,2 & 3) detailing all computerised planning work. The report must be typed and submitted in a professional format.
Attachment:- Group Project.rar
Evaluate the final outcome of the project
: Analyze a project you have worked on. The project may have been at home, at work, or in other settings (for example, church or school).
|
Research on a local australian-based or international firm
: MBA502 - Emotional Intelligence, Cultural Intelligence and Diversity - Kaplan Business School - Presentation – Your task is to prepare a video presentation
|
Evaluating whether or not to introduce new product line
: Mary Williams, owner of Williams Product, is evaluating whether or not to introduce a new product line.
|
About the delta airlines case
: The case begins with Roberto Ioriatti, Vice President of Atlantic & Pacific Pricing and Revenue Management at Delta Air Lines,
|
Develop a project execution plan
: EPM5700 - Project Management and Information Technology - Victoria University - Group Project - Project Execution Plan- develop a project execution plan
|
Besides the seven deadly ethical sins identify
: Besides the seven deadly ethical sins identify and discuss another ethical dilemma that arises from the use of content marketing please explain?
|
What are the possible legal and ethical future implications
: NUR120 - Introduction to Professional Nursing Assignment - Case Based Essay Question, Charles Darwin University, Australia. What the possible legal implications
|
High emotional intelligence is at heart of effective teams
: High emotional intelligence is at the heart of effective teams.
|
What is the context of the communication
: What messages were exchanged? What (if any) noise distorts the message? How is feedback given? What is the context of the communication?
|