Develop a preliminary design, including flow rates

Assignment Help Civil Engineering
Reference no: EM13535607

Develop a preliminary design, including flow rates, pipe sizes, and pipe slopes for a trunk sewer to be laid in the development shown in the accompanying figure from 6th to 1st Streets along Peavy Avenue.

Assume the following data apply

(a) Saturation population and flow data

Zoning Type of development Saturation population density, person/ha Wastewater flow,

L/capita. d

Residential Single-family dwellings 30 380

Residential Duplexes 50 310

Residential Low-rise apartment 100 260

Residential High-rise apartment 160 220

Peaking factor for residential area

(b) Wastewater flow and peaking data for commercial and industrial areas and institutional facilities.

Area/facility Flow (basis) Value Peaking factor

Commercial m3/ha.d 32 1.5

Industrial m3/ha.d 60 2.2

School L/student.d 80 3.5

Park L/person.d 30 4.0

(c) The average daily attendance at the school is 1000 students.

(d) Assume parks usage is 500 persons/d

(e) Assume flow from upstream area is equal to 0.005 m3/s.

(f) For infiltration allowance

(i) For residential areas, obtain the peak infiltration values from the following figure.

(ii) For commercial, industrial, and institutional areas, also obtain the peak infiltration values from the same figure. However, use only 50 percent of the actual area to compute the infiltration allowance.

(g) Assume inflow can be neglected.

(h) For the hydraulic design equation use the Manning equation with an n value of 0.013.

(i) The local sewer code specifies 200 mm as the smallest pipe permissible.

(j) Use 0.75 m/s as the minimum velocity during the peak flow conditions.

(k) The minimum depth of cover over the top of the sewer is 2.0 m.

Reference no: EM13535607

Questions Cloud

What is normally consolidated clay : Compute the nominal shear strength of an M10 x 7.5 of A 572 grade 65 steel
Compute the probable settlement of the building : The construction of a multi storied building started in January 1989 & was completed in June 1990. The total consolidation settlement of the building was estimated to be 8 cm.
Determine the quantify the losses in this system : At Point A, in a pipeline carrying water (γ=62.4 lb/ft^3) the diameter is 4.0 ft, the pressure is 10 psi, and the velocity 4 ft/s. At point B, 6ft higher than point A, the diameter is 2 ft and the pressure is 2ps
What is the average crack spacing for that reinforcement : Compute the effective composite modulus of subgrade reaction (please consider the subbase, the presence of a relatively shallow rock foundation, and the potential loss of support)
Develop a preliminary design, including flow rates : Develop a preliminary design, including flow rates, pipe sizes, and pipe slopes for a trunk sewer to be laid in the development shown in the accompanying figure from 6th to 1st Streets along Peavy Avenue.
Compute the atomic packing factor for cesium chloride : Compute the atomic packing factor for cesium chloride assuming thatthe ions touch along the cube diagonals. Ionic radii ofCs+ and Cl- are 0.170 nm and 0.181 nm,respectively
Show calculations to justify your answer : Are installed together? Show calculations to justify your answer and sketch a specific energydiagram to illustrate the process of changes in flow depth in eachcase.
In what ways do the experts foresee the use : Review the literature and analyze the strengths and weaknesses of both virtualization and cloud computing in providing secure and trusted systems.
Describe the security implications of using these technology : Describe the security implications of using these technologies and how risk will be mitigated from a network hardware and software perspective.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate the axial and radial strains and volumetric strain

A cylindrical soil, 75mm in diameter and 150 mm long, is radially compressed. The length increases to 153 mm and the radius decreases to 37.2 mm. Calculate: a) The axial and radial strains b) The volumetric strains

  Calculate the fluid velocities at the two ends

Assume frictionless flow in a long, horizontal, conical pipe. The diameter is 12 inches at one end and 6 inches at the other. The pressure head at the smaller end is 16 feet of water.

  Calculate ultimate bod where discharge and river meet

Wastewater from a paper mill contains ultimate BOD of 200ppm and DO of 3ppm, water is discharged at a rate of 100,000 gallons per day into a river, the river has a flow of 1 million gallons per day with no BOD

  Determine euler buckling stress and euler buckling load

A 12 foot W14 X 22 column with pinned ends is axially loaded. The max load it can carry is 34 ksi. Determine (a) Euler buckling stress, (b) Euler buckling load. (A = 6.49 in^2) (ry = 1.04 in) (Iy = 7.00 in^4)

  Corners successively along the e-w lines

Corners successively along the E-W lines

  Design lined trapezoidal channel to carry on longitudinal

Design a lined trapezoidal channel to carry 20 m^3/sec on a longitudinal sloe of 0.0015. The lining of the channel is to be float-finished concrete (n=0.015). Consider (a) the best hydraulic section and (b) the section with side slopes 1.5:1 (H:V)

  Speeds could a vehicle be operated without sliding inward

If the actual coefficient of sliding friction on icy pavementis 0.05, theoretically within what range of speeds could a vehiclebe operated without sliding inward or outward for the following problems.

  Will the ship take more or less draft when steaming

A 245 m ship has a displacement of 3x10^8N,and the area defined by the waterline is 3550m^2. will the ship take more or less draft when steaming from salt water to fresh water How much will it settle or rise

  Determine the moment of the couple formed by the two forces

Two parallel 40-N forces are applied to a lever. Determine the moment of the couple formed by the two forces (a) by resolving each force into horizontal and vertical components and adding the moments of the two resulting couples

  What is the diameter d of the smallest-sized particles

In a hydrometer test, the data recorded at 60 minutes after the start of the test are as follows: Gs = 2.6, temperature of water T = 24°C and L = 9.2 cm. What is the diameter D of the smallest-sized particles

  What is the oil flowrate in stb

Two wells had been drilled on 40-acre spacing. Well 1 is injectionand Well 2 is producing well. Downhole injection pressure is 8500psi, and bottomhole pressure in producing well is 2400 psi.

  What was students associated perception per reaction time

the student strikes the sign at a speed of 25 mi/h. if the student was traveling at 55 mi/h when the sign was first spotted, what was the students associated perception/ reaction time

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd