Reference no: EM13708233
Develop a preliminary design, including flow rates, pipe sizes, and pipe slopes for a trunk sewer to be laid in the development shown in the accompanying figure from 6th to 1st Streets along Peavy Avenue
Assume the following data apply
(a) Saturation population and flow data
Zoning Type of development Saturation population density, person/ha Wastewater flow,
L/capita. d
Residential Single-family dwellings 30 380
Residential Duplexes 50 310
Residential Low-rise apartment 100 260
Residential High-rise apartment 160 220
Peaking factor for residential area
(b) Wastewater flow and peaking data for commercial and industrial areas and institutional facilities.
Area/facility Flow (basis) Value Peaking factor
Commercial m3/ha.d 32 1.5
Industrial m3/ha.d 60 2.2
School L/student.d 80 3.5
Park L/person.d 30 4.0
(c) The average daily attendance at the school is 1000 students.
(d) Assume parks usage is 500 persons/d
(e) Assume flow from upstream area is equal to 0.005 m3/s.
(f) For infiltration allowance
(i) For residential areas, obtain the peak infiltration values from the following figure.
(ii) For commercial, industrial, and institutional areas, also obtain the peak infiltration values from the same figure. However, use only 50 percent of the actual area to compute the infiltration allowance.
(g) Assume inflow can be neglected.
(h) For the hydraulic design equation use the Manning equation with an n value of 0.013.
(i) The local sewer code specifies 200 mm as the smallest pipe permissible.
(j) Use 0.75 m/s as the minimum velocity during the peak flow conditions.
(k) The minimum depth of cover over the top of the sewer is 2.0 m.
Miller-brava is indices in a hexagonal unit cell
: Sketch crystallographic planes with the following Miller-Brava is indices in a hexagonal unit cell: (a) 1(Bar)101 ; (b) 2(Bar)112 . Mark the origin and axes. Explain your answers.
|
Determine the rate of heat transfer in the cooling section
: Moist air at 450C and relative humidity 30% (State 1) with another stream of moist air at 20?C and relative humidity 50% (State 2) in an adiabatic duct. Mass flow rate of dry air is 0.8 kg/s at section 1 and 1 kg/s at section 2. The mixed stream (Sta..
|
Determine the mass of oil in the tank
: A curde oil storage tank the tank initially contains 1000m^3 ofcrude oil. Oil is pumped into the tank through a pipe at a rate of 2m^3/min and out of the tank at a velocity of 1.5m/s through another pipe having a diameter of 0.15m. the crude oil has ..
|
Coaching model
: "Coaching Model" acronym, create your own coaching model, and define the meaning of each letter as it relates to performance management. Specify the primary reasons that you believe your model would be effective. Justify your response.
|
Develop a preliminary design
: Develop a preliminary design, including flow rates, pipe sizes, and pipe slopes for a trunk sewer to be laid in the development shown in the accompanying figure from 6th to 1st Streets along Peavy Avenue
|
Calculate the pressure at the nozzle exit
: Moist air at 35 degree C, 3 bar, and relative humidity 30% (State 1) enters a nozzle with a velocity of 50 m/s and expands in a reversible and adiabatic process such that the moist air leaving the nozzle is about to condense (State 2). Calculate the ..
|
Calculate the mass flow rate of moist air
: A non-reacting gaseous mixture with molar analysis of 74.3% N2, 4.3% O2, 7.1% CO2, and 14.3% H2O(g) enters a counter-flow heat exchanger at 800?F and 1 atm with a volumetric flow rate of 5 ft3/s (State 1) and exits at 200?F (State 2). Calculate the m..
|
How long will it take for half of the water to drain out
: An open cylindrical tank that is 2 ft in diameter and 4 ft high is full of water. If the tank has a 2 in diameter hole in the bottom, how long will it take for half of the water to drain out, if friction is neglected?
|
Electronic components of computer are cooled by air flowing
: The electronic components of a computer are cooled by air flowing through a fan mounted at the inlet of the electronic enclosure. At steady state, air enters at 18oC, 1 atm. For noise control, the velocity of the entering air cannot exceed 0.9 m/s. F..
|