Reference no: EM131357290
Problem -
Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one ranking, in 2009, SWU hired the legendary Phil Flamm as its head coach.
|
TIME ESTIMATES (DAYS)
|
DESCRIPTION
|
PREDECESSOR(S)
|
OPTIMISTIC
|
MOST LIKELY
|
PESSIMISTIC
|
CRASH COST/DAY
|
Bonding, insurance, tax structuring
|
-
|
20
|
30
|
40
|
$1,500
|
Foundation, concrete footings for boxes
|
A
|
20
|
65
|
80
|
3,500
|
Upgrading skybox stadium seating
|
A
|
50
|
60
|
100
|
4,000
|
Upgrading walkways, stairwells, elevators
|
C
|
30
|
50
|
100
|
1,900
|
Interior wiring, lathes
|
B
|
25
|
30
|
35
|
9,500
|
Inspection approvals
|
E
|
0.1
|
0.1
|
0.1
|
0
|
Plumbing
|
D, F
|
25
|
30
|
35
|
2,500
|
Painting
|
G
|
10
|
20
|
30
|
2,000
|
Hardware/AC/metal workings
|
H
|
20
|
25
|
60
|
2,000
|
Tile/carpet/windows
|
H
|
8
|
10
|
12
|
6,000
|
Inspection
|
J
|
0.1
|
0.1
|
0.1
|
0
|
Final detail work/cleanup
|
I, K
|
20
|
25
|
60
|
4,500
|
One of Flamm's demands on joining SWU had been a new stadium. With attendance increasing, SWU administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached a decision to expand the capacity at its on-campus stadium. Adding thousands of seats, including dozens of luxury skyboxes, would not please everyone. The influential Flamm had argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and everyone, including the coach, would learn to live with it. The job now was to get construction going immediately after the 2015 season ended. This would allow exactly 270 days until the 2016 season opening game. The contractor, Hill Construction (Bob Hill being an alumnus, of course), signed his contract. Bob Hill looked at the tasks his engineers had outlined and looked President Wisner in the eye. "I guarantee the team will be able to take the field on schedule next year," he said with a sense of confidence. "I sure hope so," replied Wisner. "The contract penalty of $10,000 per day for running late is nothing compared to what Coach Flamm will do to you if our opening game with Penn State is delayed or canceled." Hill, sweating slightly, did not need to respond. In football-crazy Texas, Hill Construction would be mud if the 270-day target was missed. Back in his office, Hill again reviewed the data (see Table 3.6 ) and noted that optimistic time estimates can be used as crash times. He then gathered his foremen. "Folks, if we're not 75% sure we'll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days-also for 240 days. I want to be early, not just on time!"
Discussion Questions
1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take?
2. What is the probability of finishing in 270 days?
3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.
Estimate the current cost of capital for petsmart
: Assuming that all of the existing debt gets refinanced at this new rate, estimate the value per share after this transaction. (You can assume a growth rate of 3% in perpetuity.)
|
Discuss any ethical concerns that pertain to the chosen case
: Proceed with the Assignment locating one credible source from Kaplan Library or the internet about a criminal case where the defendant used the not guilty by insanity defense. You can use the Andrea Yates case. Address the following:Provide an ove..
|
What is the project''s npv
: The IRR of this 20-year project is 10.98 percent. If the firm's WACC is 9 percent, what is the project's NPV?
|
Describe an example of a workplace email communication
: Eng 315- Describe an example of a workplace or personal email communication in which the sender (you or someone else) did not pay close attention to audience and context. Ascertain the consequences.
|
Develop a network drawing for hill construction
: Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. Develop a network drawing for Hill Construction and determine the critical path. H..
|
How we should determine the truth for at least item
: The first will be your opinion as to how we should determine the truth for at least items 1,2 & 3 above and you can add anything you think is missing.
|
How important are employee attitudes and emotions
: How important are employee attitudes and emotions as well as transparency in shaping organizational behavior - Elaborate on how employee perceptions shape organizational behavior. Are perceptions and reality always the same?
|
Why formative assessment is consider assessment for learning
: Edu. 381- Discuss how and why formative assessment is considered assessment for learning, and why summative assessments are considered assessment of learning.
|
What is the project completion date
: Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. What is the project completion date? Crash this project to 10 weeks at the least cost
|