Southwestern University:
Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents. A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one ranking, in 2009, SWU hired the legendary Phil Flamm as its head coach.
TABLE: 3.6 Southwestern University Project
|
|
|
|
Time Estimate (days)
|
Activity
|
Description
|
Predecessor (s)
|
Optimistic
|
Most Likely
|
Pessimistic
|
Crash Cost/Day
|
A
|
Bonding insurance, tax structuring
|
-
|
20
|
30
|
40
|
$1,500
|
B
|
Foundation, concrete footing for boxes
|
A
|
20
|
65
|
80
|
3,500
|
C
|
Upgrading skybox stadium seating
|
A
|
50
|
60
|
100
|
4,000
|
D
|
Upgrading walkways, stairwells, elevators
|
C
|
30
|
50
|
100
|
1,900
|
E
|
Interior wiring, lathes
|
B
|
25
|
30
|
35
|
9,500
|
F
|
Inspection approvals
|
E
|
0.1
|
0.1
|
0.1
|
0
|
G
|
Plumbing
|
D, F
|
25
|
30
|
35
|
2,500
|
H
|
Painting
|
G
|
10
|
20
|
30
|
2,000
|
I
|
Hardware/AC/metal workings
|
H
|
20
|
25
|
60
|
6,000
|
J
|
Tile/carpet/windows
|
H
|
8
|
10
|
12
|
0
|
K
|
Inspection
|
J
|
0.1
|
0.1
|
0.1
|
4,500
|
L
|
Final detail work/cleanup
|
I, K
|
20
|
25
|
60
|
|
One of Flamm's demands on joining SWU had been a new stadium. With attendance increasing, SWU administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached a decision to expand the capacity at its on-campus stadium. Adding thousands of seats, including dozens of luxury skyboxes, would not please everyone. The influential Flamm had argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and everyone, including the coach, would learn to live with it. The job now was to get construction going immediately after the 2015 season ended. This would allow exactly 270 days until the 2016 season opening game. The contractor, Hill Construction (Bob Hill being an alumnus, of course), signed his contract. Bob Hill looked at the tasks his engineers had outlined and looked President Wisner in the eye. "I guarantee the team will be able to take the field on schedule next year," he said with a sense of confidence. "I sure hope so," replied Wisner. "The contract penalty of $10,000 per day for running late is nothing compared to what Coach Flamm will do to you if our opening game with Penn State is delayed or canceled." Hill, sweating slightly, did not need to respond. In football-crazy Texas, Hill Construction would be mud if the 270-day target was missed. Back in his office, Hill again reviewed the data (see Table 3.6 ) and noted that optimistic time estimates can be used as crash times. He then gathered his foremen. "Folks, if we're not 75% sure we'll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days-also for 240 days. I want to be early , not just on time!"
Discussion Questions
1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take?
2. What is the probability of finishing in 270 days?
3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.
The bond is treated as original issue discount bond
: A newly issued 10- year maturity, 5% coupon bond making annual coupon payments is sold to the public at a price of $810. The bond will not be sold at the end of the year. The bond is treated as an original issue discount bond. What will be an investo..
|
What you add to wilsons view on the bureaucracy problem
: Explain why and provide an example to illustrate your points. Then, explain what you might add to Wilson's view on "The Bureaucracy Problem," and defend your suggestions.
|
Find out precisely what was causing the failures
: The Chief Engineer ordered the Production Department"s Project Leader, Alison Passette, to create a project immediately to find out precisely what was causing the failures and to find a way to solve the problem.
|
What will be an investor taxable income from the bond
: A newly issued 10- year maturity, 5% coupon bond making annual coupon payments is sold to the public at a price of $810. The bond will not be sold at the end of the year. The bond is treated as an original issue discount bond. What will be an investo..
|
Develop a network drawing for hill construction
: Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take? What is the probability of finishing in 270 days
|
Left to maturity and market interest rate
: Compute the price of a 6.3 percent coupon bond with 15 years left to maturity and a market interest rate of 10.4 percent.
|
How important is teamwork to your entrepreneur
: Brandon Company uses normal costing in its job-costing system. The company produces custombikes for toddlers - Write a report in which you summarise your most important learning and insights you have gathered from your (secondary) research about the..
|
Initial investment for proposed capital expenditure
: Samuels Manufacturing is considering the purchase of a new machine to replace one it believes is obsolete. The firm has total current assets of $ 913 comma 000 and total current liabilities of $ 641 comma 000. Explain why a change in these current ac..
|
What is the generic government strategic planning process
: HLS420- What is the generic government strategic planning process? What are some of the successful government strategic planning processes in use today, and why are they successful?
|