The MPS for product A calls for 100 units to be completed in week 4 and 200 units in week 7 (the lead time is 1 week). Spare part demand for Item B is 10 units per week. The bill of materials for product A is shown on the right, and the inventory records are as follows:
Item B:
Lot sizing rule: FOQ=500Lead time (wks): 2Beginning (on-hand) inventory: 100Scheduled receipts: none
Item C:
Lot sizing rule: LFLLead time (wks): 3Beginning (on-hand) inventory: 10Scheduled receipts: 200 (week 2)
A. Develop a material requirement plan for the next 7 weeks for Item B and C.
B. Will any action notices be generated? If so, explain what they are and why they must be generated.
Identify how each approach informs or impacts life, particularly as you prepare for your senior years. Discuss benefits (pros) also shortcomings (cons) of each perspective. Identify which perspective helps you to make choices as you move toward your ..
Super Discount considers the cost of flying the plane from New York to L.A. a sunk cost. By explain how many seats should Super Discount overbook the flight.
Find the probability that there will be customer waiting for service at the drive-up window.
Discuss the possibility of a fraud hotline as part of your program. How can a hotline be implemented as a tool for preventing and detecting fraud? Provide an overview of steps that you would take for a successful implementation if the corporation ..
Identify at least one metric to measure the process. Submit your flowchart for the process. Begin collecting data for the identified metric every day of the workweek. You must submit the data collected at the end of each week.
During an argument as to the merits of preventive maintenance at a printing company, the company owner asked, "Why fix it before it breacks? How would you, as the director of maintenance, respond?
Many people shy away from careers in selling, often because they think they are not outgoing enough, or because salespeople are dishonest or pushy.
Analysis of the activity network reveals an estimated project completion time of 145 working days with a project variance of 400. What is the z value for the target completion time of 180 working days? Find the closest value.
What is meant by mass customization? How can market conditions and consumer desires affect customization?
What would you have done differently? Be specific. NOTE: Do not name the organization. Just use the XYZ as the name.
Given Gasoline production function of QG = 72MG 1.5 MG2, illustrate what is gasoline marginal profit. Given fibre production function of QF = 80MF 2MF2, illustrate what is fibre marginal profit.
Discuss circumstances when outsourcing should be considered, and whether outsourcing will add to the competitive advantage of a firm
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd