Develop a loading chart for the project resources

Assignment Help Project Management
Reference no: EM131131576

Question:

Not sure how to do backwards and forwards network?

1122_Figure.jpg

The book we use is Jeffrey K. Pinto.(2016). Project Management Acheiving Compettitve Advantage. 4th ed.Given this network plan, complete the following activities:

1. Complete the network diagram by conducting a forward and backward pass through the network. Compute the early/late start time, early/late finish time, and slack time for each activity

2. What is the project duration?

3. What is the critical path of this network?

4. Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.

5. Using the resource loading chart, now compute the early/late start time, early/late finish time, and slack time for your project. Illustrate this new resource constrained network in a network diagram.

6. Complete the resource activity schedule.

7. For the new network, what is the new project duration?

8. Which activities are now critical?

Reference no: EM131131576

Questions Cloud

Examine which position you support and defend your position : Evaluate both the advocates' position and the critics' position. Determine which position you support and defend your position.
Calculate the magnitude of this induced emf : The automobile travels at 68.0 km/h on a horizontal road where Earth's magnetic field is 50.0 µT, directed toward the north and downward at an angle of 65.0° below the horizontal.Calculate the magnitude of this induced emf. V
Define the negotiating goal : List the major issues in the negotiation related to achieving the goal. Define their relative importance of each issue, and define the bargaining crux. Define the interests.
Explain the current market conditions facing your product : Write a 2,000-word analysis of the current market conditions facing your product. Introduce what you are going to write about,write about it and then in the conclusion highlight a few specifics from the body of your paper.
Develop a loading chart for the project resources : Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E).
Find the acceptable range of prices in terms of cars : Find the acceptable range of prices in terms of cars that 10 pianos will trade for. Show your work. Make sure your answer is clearly labeled
Do you believe immigrants really hurt us workers wages : Do you believe immigrants really hurt US workers wages? Why or why not? Is our current immigration laws costing the US our competitive edge in innovation? Should immigration laws be reformed or toughened?
What is the final temperature of the mixture : If the heat absorbed by the water in Part (5) came from the condensation of steam initially at 100 oC, how much steam condensed?
Explain the concept of of the theory of consumer behavior : In more than 500 words explain the concept of of the theory of consumer behavior

Reviews

Write a Review

Project Management Questions & Answers

  Procedure to solve a maximization problem requires

Using a graphical solution procedure to solve a maximization problem requires

  Explaining importance ethical and legal responsibilities

Explain the importance ethical and legal responsibilities in the research project.

  Potentially affected by the issue

What issue/topic is the article addressing? Who is potentially affected by the issue/topic?

  It project managers and traditional project managers

What is the difference between IT project managers and traditional project managers if there are so many similarities in project management discipline

  Construct an argumentfor or againstthe notion

Construct an argumentfor or againstthe notion that an individual's privacyismore importantthan any otherconsideration like security,childcare etc. in the workplace,Use ethical theory to support your position. Using APA referencing system

  Balance productivity with quality

Explain what factors need to be considered when balancing productivity with quality in a service organization

  You are a project manager in the marketing department for a

you are a project manager in the marketing department for a global investment management firm lrh financial. the

  Earned value management

Project managers often use Earned Value Management (EVM) if they want to compare the status of their projects to their project plans. Using the same project from Assignment 3, develop a project scenario to explain the amount of work that you have ..

  Find the cost benefits analysis

Explain how do you ensure that the requirements are fully developed and vetted by project SMEs so that the risk of a scope increase is low?

  Describing tort risk exposure for organization

Describe the tort risk exposure for any organization with which you are familiar with.

  Why executives still seemed apprehensive after presentation

Discuss the main reasons why the executives still seemed apprehensive even after the consultant's presentation.

  Purposes behind having a performance appraisal system

Which of the following reasons does NOT support the purposes behind having a performance appraisal system:

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd