Reference no: EM132607753
Supply Chain Analysis and Design
Case: Disaggregation
Considerable research during the last two decades has concentrated on aggregate production planning, inventory control, and scheduling. Aggregate planning procedures, which have been proposed for both manufacturing and service organizations, help determine monthly (or quarterly) output, inventory and manpower aggregates. Inventory and scheduling procedures, using the aggregate decisions as input, tend to focus on such short-term decisions as (i) the sizing and timing of production (purchase) orders for specific items, (ii) sequencing of individual jobs (orders), and (iii) short-term allocations of resources to individual activities and operations. The total process of going from aggregate plans to more detailed plans can be called disaggregation.
Disaggregation is an important issue in manufacturing as well as service organizations. Depending upon the nature of the production system, disaggregation decisions in a manufacturing organization may exist on one or more of the following three levels:
1. Given aggregate decisions on output and capacity, determine the timing and sizing of specific final product production quantities over the time horizon (sometimes referred to as a master schedule).
2. Given the timing and sizing of final product production quantities, determine the timing and sizing of manufactured (or purchased) component quantities.
3. Given the timing and sizing of component quantities, determine the short-term sequences and priorities of the jobs (orders) and the resource allocations to individual operations.
The taxonomy shown on the left side of Figure 1 provides the framework with which the three levels of disaggregation in manufacturing organizations.
Disaggregation problems in service organizations possess the complicating characteristics of stringent response time requirements, time dependent demand rates, and no finished goods inventories to smooth production rates. Disaggregation decisions in service organizations also exist at three levels:
1. Given aggregate decisions on output and capacity, allocate manpower and other resources to specific operations over the time horizon (sometimes referred to as the staff sizing problem).
2. Given the allocation of resources to specific operations, determine the shift schedules and crew assignments of employees.
3. Given the shift schedule assignments, determine short-term adaptations, reallocations between operations, and priorities of the service requirements.
The right half of Figure 1 provides a basis for describing disaggregation problems in the service organizations.
Watch
Watch the following videos:
• Definitions (from 41:21 onward)
• Disaggregation
Problem
Renova's problem is to develop a disaggregate production plan (Economic Lot Schedule) for five SKUs (white, blue, red, green, and pink) of a product to determine the optimal cycle length in order to minimize the total cost (or equivalent objective). The notations are presented in Table 1.(attached) However, you need to define new variables if required.
Part A
Demand and inventory on hand for five SKUs are presented in Table 2(attached):
Given that the demands are deterministic and in manhours, and the available manhours (????) for a cycle is 3000,
i. determine the sequence of producing the SKUs and show it in a simple graph.
ii. develop a linear programming model (in MS Word) and then solve it in Excel.
iii. explain the findings in details (MS Word)
iv. develop a table in which inventory position of all SKUs is presented for periods of switching the production for each SKU (MS Word and MS Excel). For inventory positions, round to the nearest integer and compute the sum of inventory on hand for each period.
v. Is maximization of T in conflict with the JIT paradigm where we try to achieve the minimum manufacturing cycle time?
Part B
Suppose we keep the information regarding the demand, inventory on hand, and the total production manhours from Part A. In this section, we want to avoid keeping excess inventory before the production begins. In other words, Renova starts to produce the items only when the inventory on hand is zero. You are required to
i. develop a linear programing model to provide an optimal production schedule for the five SKUs given that production starts when the inventory of an item is zero. (MS Word)
ii. Solve the problem in Excel.
iii. Discuss your findings (MS Word).
iv. develop a table in which inventory position of all SKUs is presented for periods of switching the production for each SKU (MS Word and MS Excel). For inventory positions, round to the nearest integer and compute the sum of inventory on hand for each period.
v. Explain in which model (Part A or Part B), the probability of shortages is higher. Why?. What is your recommendation?
Presentation
Organization, style, structure of sentences, flow of information, presenting the mathematical expressions in right format, citations and referencing, structure of tables and figures and the associated captions, and overall presentation.
Attachment:- Supply Chain Analysis and Design.rar