Develop a communication plan matrix

Assignment Help Marketing Research
Reference no: EM131655067

Vandelay Industries is going to host a "Q-school" qualifying golf tournament in Asheville, NC at the Grove Park Inn. This Q-School tournament will be one of the feeder tournaments of the PGA's Web Tour.

1. Initial Estimates of Schedule Make an educated guess for the duration of each of the work packages (elements of the lowest level of the WBS)

2. Identify the risks for the major deliverables

(1-2 risks for each level-one deliverable)

List only those occurrences that are out of the control of the project team. For example, do not list possible non compliance in the work of a vendor

Project Planning and Estimating

The fundamental mission of a project is to create value for the client, by way of meeting the specifications for the deliverable of the project, which in turn will satisfy a specific strategic objective of the enterprise.

The planning documents of the project include the specifics of crafting the deliverable itself, as well as proactive guidelines for involving the stakeholders in the decision processes of the project.

Planning the project will begin with a clear understanding of the client's strategic and financial objectives. Then, on the basis of that information, and in the light of historical data from similar projects, estimates will be made for the amount of resources required for the project, the total cost of the project, the total duration of the project, and risks that might impact the implementation and success of the project.

The skeletal framework for project plans will be provided by a hierarchical structure, which is called the Work Breakdown Structure (WBS). Although the WBS can be developed using activities or resources, the most logical method for developing the WBS is the deliverable basis.

Reading Assignments

• Integrated Project Planning, Chapter 5, Work Breakdown Structure

• Files posted with this learning module

Reference Material

• A Guide to Project Management Body of Knowledge (PMBOK® Guide), PMI, 2013

• Practice Standard for Work Breakdown Structure, PMI, 2006

• Project Stakeholder Management, by Lund and Jepsen, 2014

• Project Management Communication Tools, by Dow and Taylor, 2015

Assignments : Individual Assignment 4I - Stakeholder List

According to PMBOK (PMI, 2013), project stakeholders are individuals, groups, or organization who may affect, be affected by, or perceive themselves to be affected by a decision, activity, or outcome of a project.

Vandelay Industries is going to host a "Q-school" qualifying golf tournament in Asheville, NC at the Grove Park Inn. This Q-School tournament will be one of the feeder tournaments of the PGA's Web.com Tour.

Develop a list of at least 30 stakeholders for the golf tournament:

• List only specific, relevant, and meaningful, stakeholders (no generic, frivolous, or fictitious, stakeholders)

• Be sure to include the PM team!

• Make an educated guess for the nature of the impact of each stakeholder on the project. Be specific on the nature, ie: interest in the project, what and how they affect the project, level of impact

• Divide the stakeholder list into 5-7categories

Make an educated guess for the overall impact of each category on the project. Be clear and specific on the nature and level of impact.

Post your assignment to the 4I dropbox.

Assignments : Team Assignment 5Ta - Stakeholder Communications

Use your stakeholder lists developed last week as the starting point of this assignment. Discuss the different stakeholders you came up with individually and use them for this team assignment.

Develop a communication plan matrix for each stakeholder category. For each category specify:

• Whether the information should regard:

Intended use (strategic objective of the project)

Impact of the deliverable on economy, environment, people, etc.

Cost of project

Duration of project

Quality of project

Other issues

• Whether the information should be detailed or summarized (and why)

• Who should present/own the information (team members, the project manager, chief budget officer, etc.)

• The medium of transmission (face to face, phone, email, meeting, etc.)

• The frequency of transmission Do not present generalities, give specifics. Post this assignment to the 5Ta dropbox.

Team Assignment 5Tb - Develop a Work Breakdown Structure

For this part of the assignment, you will be creating a WBS and estimating cost, schedule, and identifying major risks. I suggest you use Excel for the assignment. On the first tab, you can place your write up in a text box, create your WBS on another worksheet tab, other sheets for the cost, schedule, and risk assessment. Using Excel will make organization easy, and any calculations automatic.

If you want to create your WBS graphic in another program, you can do that and paste it into your spreadsheet. Remember, you can add textboxes in Excel worksheets. Color code your tabs and remember to use formatting to draw my attention to your answers.

If I have to "search all over" for what I'm looking for, you haven't created your deliverable well. Think about how a board room boss, or your project sponsor, would want to see this information.

a. Develop a WBS for the golf tournament project

• The deliverable elements you created in 2T should be refined to make up the "level one" of your WBS (the "Q-school golf tournament" is level zero)

Divide each major deliverable element into seven-nine lower elements known as "work packages"

Present your WBS graphically

Maintain a reasonable consistency in the level of detail of the lowest level elements. Not all branches need to go to the same level, but the significance of the lowest-level items should be similar. An example of this inconsistency is where one of the lowest level elements describes a vendor selection, while another lowest level element describes game day grass cutting.

Use number notation, e.g. 1.2.5, to highlight the lineage of each WBS element. Add a prefix of W to all element numbers.

b. Initial Estimates of Cost

• Provide an educated guess for the cost of each of the work packages (the lowest level of the WBS).

Roll up these elemental costs to determine the overall cost for each of the major elements (level one elements)

Roll the cost of the major elements to determine the cost of the total project.

c. Initial Estimates of Schedule

• Make an educated guess for the duration of each of the work packages (elements of the lowest level of the WBS)

d. Identify the risks for the major deliverables (1-2 risks for each level-one deliverable)

• List only those occurrences that are out of the control of the project team. For example, do not list possible non-compliance in the work of a vendor


Attachment:- ElementalEstimate.rar

Reference no: EM131655067

Questions Cloud

Discuss the relationship between given conditions : This procedure has conditions placed on the expected value of each cell. Discuss the relationship between these two conditions.
Discuss about law enforcement officers : Law enforcement officers have a search warrant to search a house for heroin and to search the person of the house owners
What tests should doctors conduct to confirm this diagnosis : Doctors suspected Robert's symptoms were caused by an infection he developed while on safari. What tests should doctors conduct to confirm this diagnosis
Proplem need to settlement : Read the laws Kasans, Girmany and UCC 2-316. so you will find some points hlep me to aviod to pay for Eurobilders - Proplem need to settlement
Develop a communication plan matrix : Identify the risks for the major deliverables.List only those occurrences that are out of the control of the project team.
Discuss the similarities of the two methods : However, besides all the similarities of the two methods, the hypothesis test of the difference between two proportions has two advantages.
What does this algorithm compute : What does this algorithm compute?
Define the primary policing agencies : The department has emerged as one of the primary policing agencies in the state. It has become a modern police department
Fluent with the java programming syntax : Describe at least three strategies that you will take to become fluent with the Java programming syntax.

Reviews

Write a Review

Marketing Research Questions & Answers

  Write the first section of the marketing plan

create a complete Marketing Plan by the end of the course. You will write the first section of the Marketing Plan for this assignment. Use the guide to identify the sections of the Marketing Plan and the marketing elements contained therein. This ..

  Designing vb applications across multiple platforms

This assignment will contain two (2) Parts: Written Paper and Visual Basic Prototype. The Visual Basic Prototype is not included in the total page count but is included in the evaluation of your assignment. You must submit both parts for the compl..

  Explain and evaluate contingencies

Explain and evaluate contingencies

  What marketing research might mean to a firm

Laurent-Perrier, number three in terms of worldwide sales of champagne, has been getting its house in order.- Discuss what marketing research might mean to a firm.

  Explain the evolution of dunkin donuts

Determine the substantive ways in which the retail information has helped both businesses to evolve.

  Should there be greater government regulation

Should there be greater government regulation with respect to selling to vulnerable consumers?

  A role in the marketing plan and implementation

In any organization you will serve a role in the marketing plan and implementation. This final project will prepare you for that role.

  What are the major differences between sales and marketing

George Kline is a sales representative for Southern-Swim, a swimming pool service and supply company. Southern-Swim sells the chemicals needed for pool maintenance as well as pool accessories like slides, ladders, and diving boards. Southern-Swim ..

  Review business summary provided by sassy oil and vinegar

Review "Business Summary" provided by Sassy Oil and Vinegar. What would be so great about the product that they would purchase it?

  Develop a branding strategy for your product

Develop a branding strategy for your product that covers the brand name, logo, slogan, and at least one (1) brand extension.

  Determine the goal of the chosen companys social media

Determine the goal of the chosen company's social media campaign, and examine whether or not the company's social media campaign has the same effect as that of its traditional media marketing. Justify your response. Note: Include the source of you..

  Describe a public relations marketing strategy

Describe a public relations marketing strategy that a firm may use to enhance brand awareness and/or the company's image.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd