1. Using the 50-50 Rule, what is earned value for this project?
2. Using the 0-100 Rule, what is earned value for this project?
Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.
Budget
Begun?
Complete?
Actual cost
Earned Value
Task A
3,100
Yes
Task B
4,000
4,500
Task C
2,500
2,250
Task D
No
3,500
Task E
Task F
0
You make $12 dollars per hour, plus time and a half for each hour over 40 hours that you work in a week. How many hours do you need to work in a week to earn $588?
Let f be a function that is differentiable for all real numbers. The table gives the values of f and its derivative f' for selected points x in the closed interval -1.5 0 for -1.5
What types of information can you get from a linear function or an exponential function? Why is it important to know which type of function to use when determining the correct outcome?
In 1900 ,a certain country's population was 72,028,751 and its area was 2,967,929 square miles. In 1980 ,the country's population was 276,948,879 and its area was 3,730,271 square miles. a. Find the population density of the country, to the neares..
The number B of bacteria in a Petri dish culture after t hours is given by.
p A boat takes 6 hours to go downstream and upstream a certain distance. It takes 4 hours to travel twice the distance downstream. Which of the following is the ratio of the speed of the boat in still water to the speed of the river? Indicate the cor..
Values of three functions are given in Table, rounded to two decimal places. Two are power functions and one is an exponential.
In a particular scheme for numerically modeling one-dimensional fluid flow, the successive values, u n , of the solution are connected for n ≥ 1 by the difference equation c ( u n+1 - u n-1 ) = d ( u n+1 - 2u n + u n-1 ).
An anchor weighing 125 lb in water is attached to a chain weighing 4 lb/ft in water. Find the work done to haul the anchor and chain to the surface of the water from a depth of 50 ft.
Consider the function f : [-π, π] → R given by f(x) = (e-x)*sin x, Calculate local maxima/minima and points of inflection of f(x)
question a 20-ft-by-30-ft swimming pool is filled with water. the depth is measured at 5-ft intervals starting at one
The perimeter of a swimming pool is 91m. The width is 5m more than half the length of the pool. Find the length and width of the pool.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd