Determining es-ef-ls-lf and slack for each activity

Assignment Help Project Management
Reference no: EM1335747

After consulting with Butch Radner, George Monohan was able to determine the activity times for constructing the weed-harvesting machine to be used on narrow rivers. George would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. The activity times are shown in the following table:

Activities and Time (in Weeks):
A - 6
B - 5
C - 3
D - 2
E - 4
F - 6
G -10
H - 7

 

Reference no: EM1335747

Questions Cloud

Illustrate what affect might our concern for the baby : Illustrate what affect might our concern for the baby boomers reaching retirement age, and the smallest number.
Criminal justice professionals : Describe ways to improve nonverbal communication in 700-1,050 words. Be sure to discuss the following questions.
Define how a databses management system : describe how a databses management system (DBMS) and data mining can help a motor vehicle maintenance center improve its services, and what tables would be needed in such a database. Also what additional way can the DBMS and data mining be used to..
Explain what is the present value : Explain What is the present value of $10000 received and Six years from today when the interest rate is 2% per yr
Determining es-ef-ls-lf and slack for each activity : George would like to determine ES, EF, LS, LF, and slack for each activity.
Decision making technique using a pro vs cons : the rational decision making technique using a pro vs cons approach for deciding on whether or not to start a business in the island of Kava.
Suppose that the income effect of the tax induced price : Suppose that the income effect of the tax induced price change is negligible, the excess burden of the tax will be.
Explain the complete erd containing all primary keys : A tiny college wants to keep track of the history of all administrative appointments (date of appointment and date of termination).
Constructing a network for activities : The activities that are necessary to build one of these experimental weed-harvesting machines are listed in the following table. Construct a network for these activities.

Reviews

Write a Review

Project Management Questions & Answers

  Prepare a monthly profit report

Prepare a "Monthly Profit Report", Create this report using the results of your ABC overhead allocation.

  Analysis of the overall project risk

Analysis of the overall project risk

  Teleological and deontological frameworks

List and discuss in depth the three teleological frameworks and the three deontological frameworks.

  Resource constrained

How does the new duration compare with the estimated completion date generated from Part 1? What does this tell you about the impact resources can have on a schedule?

  Primary focus of the functional manager

What is the primary focus of the functional manager? Would you recommend this type of management for a project?

  New product development

You are required to submit a written assignment relating to New Product Development.

  Advantages and disadvantages of using erp

What are the advantages and disadvantages of using an ERP system? What is the relationship between information silos and enterprise resource planning?

  Define the term product

Using a relevant product within the hospitality or tourism sector answer the three following questions. Define the term product. Describe the four main product levels that applies to your chosen product.

  Constructing a network for activities

The activities that are necessary to build one of these experimental weed-harvesting machines are listed in the following table. Construct a network for these activities.

  Factor which influence the team dynamics

Determine which factor is influencing the team dynamics and why.

  Importance of incorporating a budget into project schedule

Explain the importance of incorporating a budget into a project schedule.

  Major risks to organization when implementing and using it

What are the major risks to the organization when implementing and using IT?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd