Q1) Given following financing project being considered by venture film, determine critical path probability of completion by 17 weeks. By 24 weeks. By what date is management 90 percent sure completion will happen?
Times (weeks)
Activity
Optimistic
Most Likely
Pessimistic
1-2
5
11
1-3
10
1-4
2
8
2-6
1
7
13
3-6
4
3-7
3-5
4-50
6
5-72
14
6-71
If venture firm can complete project for customer within 18 weeks, it will get a bonus of $10,000. But if project delays beyond 22 weeks, it should pay penalty of $5,000 due to lost customer impact. If firm can select whether or not to bid on this project, what must its decision be if project is only breakeven one normally?
Find the range and the standard deviation of the times.
Find a 90% confidence interval for the difference between the proportion of men and the proportion of women who approved of Reagan's performance. What assumption do you make to use this method?
Determine the mode for this distribution. Describe why you can't calculate the mean number of times using data in the table.
Test whether there is difference in the two population mean. Use p-value approach
A sample of 50 provided a sample mean of 14.15. The population standard deviation is 3.
Is it reasonable for the manufacturer to claim that the drill bits will last 2.5 hours?
Construct a grouped frequency distribution using six classes.
The sample proportion of large gloves for each location is and . (Round your answers to 4 decimal places.)
Given that both balls selected are white what is the probability that bowl 3 was selected?
Compute fraction of the employees cost between $1,500 and $2,000 per year? Evaluate percent that didn't have any dental expense.
Calculate descriptive statistics for each stock and the S&P 500. Comment on your results. Which stocks are the most volatile? Calculate the value of beta for each stock.
Calculate the range, variance, and standard deviation for these sample data.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd