Assignment : Project Schedule Changes
You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.
In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.
Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.
You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.
You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.
Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation.
Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.
Can you reject the null hypothesis
: To test the hypothesis that the average price is $14.25 versus the alternative hypothesis that it is not $14.25, a random sample of 16 daily prices is collected. The results are x‾ = $16.50 and s = $5.8. Using α = 0.05, can you reject the null hyp..
|
Understanding of key concepts in strategic management
: The aim of the Assessment is for you to demonstrate your understanding of key concepts in strategic management and your capacity to craft a professional document. It will be very good preparation for your dissertation
|
How your personality type influence your job performance
: Do you agree with the results of your assessment? Based on the results of your assessment, what do you see as your strengths and weaknesses? How might your personality type influence your job performance?
|
Does the analyst have statistical evidence
: An analyst tests this claim by looking at a random sample of 50 stocks and finds a sample mean of 3.8% and a sample standard deviation of 1.1%. Using α = 0.05, does the analyst have statistical evidence to reject the claim made by the magazine?
|
Determine your best course of action for bringing project
: You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.You originally were told the permits would only take 2 weeks to obtain but the contractors ar..
|
Whether you believe customer satisfaction has improved
: Use an α of your choice, and determine whether statistical evidence indicates a change in customer satisfaction. If you determine that a change did occur, state whether you believe customer satisfaction has improved or deteriorated.
|
Describe the organization and purpose of chaebols
: Explain the organization and purpose of chaebols. Identify the positive and negative characteristics of chaebols for both local and global economy. Also, explain the role they play in the South Korean economy.
|
Read an article and write a response
: Read an article with a clearly named author and write a response to it that uses five quotes from the original. Use a different form of quote set-up for each quote- don't repeat the same one for all five quotes
|
State same result at different levels of significance
: Advise the authority on what should be done. Explain your recommendation. Could you state the same result at different levels of significance? Explain.
|