Reference no: EM132547974
Moonbeam Company
Moonbeam Company uses a standard cost system for its production process and applies overhead based on direct labor hours. The following information is available for September when Moonbeam produced 5,000 units:
Standard: DLH per unit3.00
Variable overhead per DLH$1.80
Fixed overhead per DLH$3.25
Budgeted variable overhead$27,250
Budgeted fixed overhead$49,500
Actual: Direct labor hours16,000
Variable overhead$31,325
Fixed overhead$49,750
Question 1: Refer to Moonbeam Company. Using the four-variance approach, what is the variable overhead efficiency variance?
a.$1,800 F
b.$ 250 U
c.$1,800 U
d.$ 250 F