McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:
- Activity 1: Measure office room dimensions
- Activity 2: Estimate cost
- Activity 3: Material requisition
- Activity 4: Workforce requisition
- Activity 5: Special tool requisition
- Activity 6: Installation
- Activity 7: Inspection and customer acceptance
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities
|
OT
|
MT
|
PT
|
Activity 1
|
4
|
6
|
14
|
Activity 2
|
5
|
12
|
16
|
Activity 3
|
7
|
15
|
23
|
Activity 4
|
13
|
16
|
28
|
Activity 5
|
17
|
20
|
35
|
Activity 6
|
20
|
32
|
50
|
Activity 7
|
5
|
6
|
13
|
You must also do the following:
- Determine the expected completion time and the variance for each activity
- Determine the total project completion time and the critical path for the project
- Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
- What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
- Define project management and the necessary requirements.
- Analyze implications of changes in project scheduling.
- Evaluate application of project management techniques in terms of the firm's business operational goals and requirements.
Please submit your assignment in an APA-formatted paper.
Submitting your assignment in APA format means, at a minimum, you will need the following:
- Title page: Remember the running head. The title should be in all capitals.
- Abstract: A summary of your paper, not an introduction. Begin writing in third-person voice.
- Body: The body of your paper begins on the page following the title page and abstract page and must be double-spaced (be careful not to triple- or quadruple-space between paragraphs). The type face should be 12-pt. Times Roman or 12-pt. Courier in regular black type. Do not use color, bold type, or italics except as required for APA-level headings and references. The deliverable length of the body of your paper for this assignment is 2-3 pages. In-body academic citations to support your decisions and analysis are required. A variety of academic sources is encouraged.
- Reference page: References that align with your in-body academic sources are listed on the final page of your paper. The references must be in APA format using appropriate spacing, hang indention, italics, and upper- and lowercase usage as appropriate for the type of resource used. Remember, the Reference Page is not a bibliography but a further listing of the abbreviated in-body citations used in the paper. Every referenced item must have a corresponding in-body citation.
In regards to public leadership
: In regards to Public Leadership, what are the major differences and similarities between the contingency theory and the path-goal theory? Do you believe the two theories are completely different or somewhat intertwined in their approaches? Why or why..
|
What biggest social problems associated with urbanization
: You are expected to respond to at least two peers. It is acceptable to combine responses into one scholarly paragraph (ten - twelve sentences) when responding to peers. Please state the names of peers before responding- What are the biggest social..
|
When employers seek to monitor employees actions
: When employers seek to monitor employees' actions through a video surveillance system, are there ethical obligations that constrain—or should constrain—employers? If so, what are those obligations, and how are they satisfied? Does it matter whether t..
|
Determine the final pressure and the heat transfer
: A 1-m3 tank containing air at 25?C and 500 kPa is connected through a valve to another tank containing 4 kg of air at 60?C and 200 kPa (Fig. P3.232). Now the valve is opened and the entire system reaches thermal equilibrium with the surroundings a..
|
Determine the total project completion time
: You must also do the following: Determine the expected completion time and the variance for each activity and Determine the total project completion time and the critical path for the project
|
Security-exchange commission on the business environment
: As we explore the role of the Security and Exchange commission on the business environment (Chapter 12 Reading), we see that there are many rules and regulations that must be followed in order for a publically traded business to operate in the United..
|
Identify commonality and difference in probation and parole
: Probation and parole are both types of community supervision for offenders being supervised by correctional agencies. While these forms of community supervision have similarities, they are intended for different types of offenders.
|
Representative of the population
: The _______________ probability distribution can be used to estimate the number of vehicles that go through an intersection during the lunch hour. act(s) as a representative of the population.
|
Calculate the work done during this process
: A piston of 4 lbm is accelerated to 60 ft/s from rest. What constant gas pressure is required if the area is 4 in.2, the travel distance is 4 in., and the outside pressure is 15 psia?
|