Determine the total estimated cost of project

Assignment Help Accounting Basics
Reference no: EM131517705

Question: A contractor has a contract to remove and replace the existing landscape and sidewalks around an office building. The work includes demolition of the existing landscaping and sidewalks, importing fill and grading around the office building, constructing new concrete sidewalks, and new landscaping. The contractor uses the cost codes. The original estimate for the demolition was $30,000 and a $5,000 change order has been approved to remove some unexpected debris found during the demolition. The demolition work has been completed at a cost of $33,562. The original estimate for the fill and grading was $17,500 and a $2,000 change order for importing additional fill to replace the debris has been approved.

The fill and grading costs to date are $17,264 and the cost to complete has been estimated at $2,236. The original budget for the labor to pour the concrete was $19,200 and no changes have been made. The concrete labor has been subcontracted out for $19,200, for which the contractor has received a bill for $15,200. The original budget for the concrete for the sidewalks was $9,900 and no changes have been made. The contractor has spent $7,425 for concrete and estimates that $1,950 of concrete will be needed to complete the project. The original estimate for the landscaping was $37,500 and no changes have been made. The landscape work has been subcontracted out for $37,500. The landscaping work has yet to start and no bills have been received. Determine the total estimated cost at completion for the project and the variance for each cost code.

Reference no: EM131517705

Questions Cloud

The cognitive psychology associated with language : Discuss the Cognitive Psychology associated with language and their functions.
Final case study and strategic plan : Read What's Driving Porsche? And History of Porsche AG - FundingUniverse. From the perspective of an executive with the firm, prepare a strategic plan.
What is expected return-volatility of portfolio consisting : What is the expected return and volatility of a portfolio consisting of 69 % Ford Motor stock and 31 % of Molson Coors Brewing? stock?
Write clearly and concisely about long-term care management : Assess the immediate staffing needs at BNH. Write clearly and concisely about long-term care management using proper writing mechanics
Determine the total estimated cost of project : A contractor has a contract to remove and replace the existing landscape and sidewalks around an office building. The work includes demolition of the existing.
Portfolio of two stocks has smallest possible volatility : What portfolio of the two stocks has the smallest possible volatility?
Mergers fail to produce value for shareholders of acquirers : Mergers fail to produce value for shareholders of acquirers in many cases. Describe and explain some reasons for mergers failure.
What cultural relativism requires of us : What cultural relativism requires of us is simply that we do not confuse our own feelings about such a custom with understanding it.
What should a diversity training program include : What should a diversity training program include? Discuss the content and how it could be assessed.

Reviews

Write a Review

Accounting Basics Questions & Answers

  How much control does fed have over this longer real rate

Hubbard argues that the Fed can control the Fed funds rate, but the interest rate that is important for the economy is a longer-term real rate of interest.   How much control does the Fed have over this longer real rate?

  Coures:- fundamental accounting principles

Coures:- Fundamental Accounting Principles: - Explain the goals and uses of special journals.

  Accounting problems

Accounting problems,  Draw a detailed timeline incorporating the dividends, calculate    the exact Payback Period  b)   the discounted Payback Period. the IRR,  the NPV, the Profitability Index.

  Write a report on internal controls

Write a report on Internal Controls

  Prepare the bank reconciliation for company

Prepare the bank reconciliation for company.

  Cost-benefit analysis

Create a cost-benefit analysis to evaluate the project

  Theory of interest

Theory of Interest: NPV, IRR, Nominal and Real, Amortization, Sinking Fund, TWRR, DWRR

  Liquidity and profitability

Distinguish between liquidity and profitability.

  What is the expected risk premium on the portfolio

Your Corp, Inc. has a corporate tax rate of 35%. Please calculate their after tax cost of debt expressed as a percentage. Your Corp, Inc. has several outstanding bond issues all of which require semiannual interest payments.

  Simple interest and compound interest

Simple Interest, Compound interest, discount rate, force of interest, AV, PV

  Capm and venture capital

CAPM and Venture Capital

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd