Determine the schedule variance

Assignment Help Project Management
Reference no: EM132348292

Determine the schedule variance, cost variance, SPI, CPI, and CSI for a project that has an actual cost at month 12 of $90,000, a scheduled cost of $100,000 and an earned value of $120,000.

Reference no: EM132348292

Questions Cloud

Discuss the four stages of project team development : Discuss the four stages of Project Team Development. Provide an example how in real life work situation these stages occur
Responsibility to a person making an enquiry : As long as you comply with any limits of your own responsibility to a person making an enquiry, there is no need to explain the nature of those limitations.
Describe the type of help they could provide : Describe the type of help they could provide; give at least two types of assistance.
What turned out to be common-cause variation : Discuss one (1) project where you used a problem-solving approach to address what turned out to be common-cause variation, Describe the experience in project.
Determine the schedule variance : Determine the schedule variance, cost variance, SPI, CPI, and CSI for a project that has an actual cost at month 12 of $90,000, a scheduled cost of $100,000
Determine the schedule and cost variance for a project : Determine the schedule and cost variance for a project that has an actual cost at month 20 of $750,000
Explain why project management : Explain why project management is often used to train future senior executives.
Process improvement framework and problem solving framework : Compare and contrast the fundamental differences between process improvement framework and problem solving framework.
Explain how to check the accuracyof business documents : NCFE Level 2 Certificate in Business Administration- Principles of Business Document production and information management

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd