Determine the rate of heat transfer from the steam

Assignment Help Civil Engineering
Reference no: EM131030582

answer the following question correctly

Saturated steam coming off the turbine of a steam power plant at 30°C condenses on the outside of a 3-cmouter-diameter, 35-m-long tube at a rate of 45 kg/h. Determine the rate of heat transfer from the steam to the cooling water flowing through the pipe.

Reference no: EM131030582

Questions Cloud

Compute the daily returns for both stocks : Compute the daily returns for both stocks. In addition, compute the returns of a Daily rebalanced Equal-weight portfolio and Value-weight portfolio. (Hint: the Datastream datatype for market value is "MV".)
Car rental agency assignment : PROJECT GUI MINIMUM REQUIREMENTS - Combo boxes, Option Buttons, and Checkboxes must interact with at least one Text Field or other control and a minimum of two fields must not be editable and their contents must be generated from other component inte..
What are the significant barriers to conversion : Conversion from an idea to an opportunity can be difficult for many organizations. What are the significant barriers to conversion that can prevent an organization for converting a good idea into value or to deliver value to an organization? Give..
Identify a house and reduce its total energy : Identify a house (bungalow or townhouse or 2/3 storey house) and reduce its total energy (gas and electricity) consumption by 30% by redesigning the walls, windows (double-pane), doors and roof in order to minimize the heat transfer losses.
Determine the rate of heat transfer from the steam : Saturated steam coming off the turbine of a steam power plant at 30°C condenses on the outside of a 3-cmouter-diameter, 35-m-long tube at a rate of 45 kg/h. Determine the rate of heat transfer from the steam to the cooling water flowing through th..
What are the most important items to add to that policy : Organizations should have policies that describe which users have access to sensitive systems and data, for what purpose, and for how long. Assume that you are an IT manager in charge of creating yourorganization's new Acceptable Use Policy. What ..
Suggest a timeline for establishing an erm plan : Provide a list of essential personnel whom you believe should be involved in creating and maintaining an ERM plan for an organization. Describe the role of each person. Suggest a timeline for establishing an ERM plan, giving your opinion on how fr..
Compare to the output of the calculator to actual survives : Compare to the output of the calculator to actual survives that's been conducted on building that's used renewables energy in Ireland to ensure the quality of work.
Calculate the duration of the nfls liability : How much money should the NFL invest in its bond portfolio today to fully fund its future liability? Calculate the duration of the NFL's liability.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Compute the force fa on the roller and the x- and y-componen

Three point loads 10,000, 7500 and 9000 kN act in line 5m apart near the surface of a soil mass. Calculate the vertical stress at a depth of 4m vertically below the centre (7500kN) load.

  Develop technical competence in problem formulation

Develop your knowledge of key principles relating to wastewater system design - Develop technical competence in problem formulation and solution in this discipline area.

  Estimate theoretical fracture strength of a brittle material

Estimate the theoretical fracture strength of a brittle material ifit is known that fracture occurs by the propagation of anelliptically shaped surface crack of length 0.2 mm(0.007874 in)

  Calculate the critical depth and critical slope

A flow of 28 m3s-1 occurs in an earth-lined canal having a base width of 3 m, side slopes of 1(vertical) to 2 (horizontal) and the Manning’s n value of 0.022. Calculate the critical depth and critical slope

  Determine the total length-depth of the pile

Using a safety factor of 2.00 and neglecting the pile dead weight, find the length of a 1' diameter circular concrete pile required to take a design load of 50 kips in a soil composed of two layers.

  Determine soils angle of internal friction under pressure

A triaxial test was performed on a dry, cohesionless soil under confining pressure of 144 kN/m^2. If the sample failed when the deviator stress reached 395.8 kN/m^2, determine the soil's angle of internal friction.

  Each month the speedy dry cleaning company buys barrel

Each month the speedy dry Cleaning company buys 1 barrel (0.160 m^3)of dry cleaning fluid . Ninety percent of the fluid is lost to the atmosphere and 10 percent remains as residue to be disposed of.

  Write down a mass balance expression for a chemical release

Write down a mass balance expression for a chemical release in a lake given the following: the lake is completely mixed, in-flow and out-flow are equal, degradation of the chemical is occurring through biodegradation (k1) and chemical transformati..

  Determine remaining load carrying capacity of cracked beam

a reinforced concrete beam with a section of 12 inches width and 24 inches depth is reinforced with 3no. 9 bars. fc'=5000psi and fy=60000psi. a 2 inch cover is used and the beam has a simply supported span lenght of 15ft.

  Estimate the diameter of the small pipe

Fluid flows steadily, at a volume rate Q, through a large pipe and then divides into two small pipes, the larger of which has an inside diameter of 25 mm and carries three times the flow of the smaller pipe.

  What would be the retention time in each tank

A water treatment plant has 6 settling tanks that operate in parallel (the flow gets split into six equal flow streams), and each tank has a volume of 600 m3. If the flow to the plant is 10 MGD, what is the retention time

  Estimate settlement of footing four years after construction

The modulus of elasticity of the sand was determined to be 10,000 kN/m^3 throughout. Using the Schmertmann's method, estimate the settlement of the footing four years after construction, using four 1 meter thick sublayers.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd