Reference no: EM131803973
The project manager is paid $30/hour and each primary (P) worker is paid $25/hour while support (S) workers are paid $15/hour.
1. Determine the project's total labor costs. Explain your results. Submit a copy of your Resource Sheet.
2. When developing the project cost plan, what things should be considered to estimate the total project costs? It may be helpful to contact actual contractors, construction companies, vendors, etc., for the tasks involved in this type of project.
Extra information:
Primary Support
Activity Responsibility Responsibility
Roof Jack Steve, Wally
HVAC Bill Scott, Trevor
Landscaping John Lynn, Beth
Paving Greg Jeff, Pat
Plumbing Max Tyler, Damian
Grading and Site Prep Sal Jim, Joe
Interior Structure Don Keith, Andrea
Foundation Construction Randy Mark, Mike
Exterior Structure Bob Dan, Ken
Electrical Seth Neil, Roy
It takes 30 days (standard 8-hour workdays, Monday through Friday) to complete each activity.