The Goodparts Company produces a component that is subsequently used in the aerospace industry. The component consists of three parts (A, B, and C) that are purchased from outside and cost 35, 30, and 10 cents per piece, respectively. Parts A and B are assembled first on assembly line 1, which produces 155 components per hour. Part C undergoes a drilling operation before being finally assembled with the output from assembly line 1. There are in total six drilling machines, but at present only three of them are operational. Each drilling machine drills part C at a rate of 50 parts per hour. In the final assembly, the output from assembly line 1 is assembled with the drilled part C. The final assembly line produces at a rate of 175 components per hour. At present, components are produced eight hours a day and five days a week. Management believes that if need arises, it can add a second shift of eight hours for the assembly lines.

The cost of assembly labor is 30 cents per part for each assembly line; the cost of drilling labor is 15 cents per part. For drilling, the cost of electricity is 2 cent per part. The total overhead cost has been calculated as $1,300 per week. The depreciation cost for equipment has been calculated as $40 per week.

a. Determine the process capacity (number of components produced per week) of the entire process.

b-1. Suppose a second shift of eight hours is run for assembly line 1 and the same is done for the final assembly line. In addition, four of the six drilling machines are made operational. The drilling machines, however, operate for just eight hours a day. What is the new process capacity (number of components produced per week)?

c-1. Management decides to run a second shift of eight hours for assembly line 1 plus a second shift of only four hours for the final assembly line. Five of the six drilling machines operate for eight hours a day. What is the new capacity?

d-1. Determine the cost per unit output for part b. (Round your answer to 2 decimal places.)

d-2. Determine the cost per unit output for part c. (Round your answer to 2 decimal places.)

e. The product is sold at $4 per unit. Assume that the cost of a drilling machine (fixed cost) is $26,000 and the company produces 9,000 units per week. Assume that four drilling machines are used for production. If the company had an option to buy the same part at $3 per unit, what would be the break-even number of units? (In your calculations, use the two-digit cost per unit from page d-1. Round your answer to the nearest whole number.)

Reference no: EM132174528

Questions Cloud

Electronic health records hold great promise : Electronic Health Records (EHR) hold great promise, yet there are still challenges to their adoption.
How did you teach your students to recognize words : Look at this word, "supercalifragilisticexpialidocious" how would you begin to pronounce it, using what decoding process?
What impact did the film have on you : What impact did the film have on you? What understanding did you have from it?
Write what your source is in the same paragraph : Biology: Include the type of information like hormones, receptors, cells, target organs, feedback, genes, development, etc. Depth is important.
Determine the process capacity of the entire process : Determine the process capacity (number of components produced per week) of the entire process.
Will saqlaim be bound by the contract : LAW 6000 – Business and Corporate Law - Will the partnership be bound by this contract? Can the other partners take action against Lance
How much value did the teacher in the classroom add : Every state has its own evaluation process for teachers. As an administrator, you are going to be evaluating your faculty.
Reason for peter preference toward brown boots : hich of the following is a likely reason for Peter’s preference toward Brown Boot’s?
What is the situation in central florida : What is the situation in Central Florida, at Valencia, Osceola County, Orange County? Who is involved? What services are available locally?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd