The Universal Manufacturing Company produces a particular product in an assembly line operation. One of the machines on the line is a drill press that has a single assembly line feeding into it. A partially completed unit arrives at the press to be worked on every 8 minutes, on average, according to an exponential distribution. The machine operator can process an average of 10 parts per hour (Poisson distributed). (20 pts)
Determine the average number of parts waiting to be worked on.
Determine the percentage of time the operator is working.
Determine the percentage of time the machine is idle.
The management likes to have operators working 90% of the time. What must the assembly line arrival rate be in order for the operators to be as busy as management would like?
illustrate at what center of gravity coordinates should the new store be located. Census tracts 103 and 105 are each projected to grow by 20% in the next year. Explain how will this influence the new store's coordinates.
Describe four (4) strategies the government must address to sustain union membership also representation among public workers.
Given the volunteers you have, the other time estimates are item K (2 hrs), item L (1 hour) also item M (4 hrs). Develop a time-phased assembly plan to prepare the gift bags.
Discuss what you think will happen to supply, demand also price of the product in the long-term. Explain why you think supply, demand, or equilibrium price will be different, if at all, in the short-term also the long-term. "
Develop your own forecast for bow rakes for each month of the next yr (yr 5). Justify your forecast also the method you used.
Explain how has the organization impacted internal department's also external participants within the supply chain.
Assure a reasonable reliability by conventional design. Set up a decision tree also evaluate expected total cost of both designs. Which design would you prefer.
Illustrate what is the probability of completing this project among 38 and 40 days. Illustrate what are the slack values for activities C and F? Interpret the meaning of their slack values.
Formulating the linear programming model which can be employed to determine the production plan that will yield the maximum possible annual profit contribution for company.
ABC Corporation sells large industrial machines which have an inventory value of Php 1.5 million every. The Corporation expects to order 500 machines during the next calendar year.
Operations Management problem relating to an organisation with which you are familiar and undertake a critical review
The room's forecast is a tool for managers throughout the hotel; it is not for the front office alone. List also examine how several other non-room departments (housekeeping, food also beverage, etc.) would use the rooms forecast.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd