Problem 1 - Economic Order Quantity

Electronic Village stocks and sells a particular brand of personal computer. It costs the store $450 each time it places an order with manufacturer for the personal computers. The annual cost of carrying/holding a PC in inventory is $170 (per unit). The store manager estimates that annual demand for the PCs will be 1200 units.

a) Determine the optimal order quantity (EOQ)?

b) What is the total annual cost (ordering & carrying/holding)?

c) What is the maximum inventory level if we order the EOQ quantity?

d) How many times we will order if we use the EOQ quantity?

e) What is the total cost is we order Q=100?

How many times we will order in this case?

Problem 2 - POQ

Discount Carpets manufactures Caskade Carpet, which it sells in its adjoining showroom store near the interstate. Estimated annual demand is 20,000 yards of carpet with an annual carrying/holding cost of $2.75 per yard. The manufacturing facility operates the same 360 days the store is open and produces 400 yards of carpet per day. The cost of setting up the manufacturing process for a production run is $720.

1. Determine the optimal order size.

2. What is the total inventory cost?

3. What is the length of time to receive an order?

4. What is the maximum inventory level?

Problem 3: Probabilistic EOQ

A computer products store stocks color graphics monitors, and the daily demand is normally distributed with a mean of 1.6 monitors and a standard deviation of 0.4 monitor. The lead time to receive an order from the manufacturer is 15 days. Determine the reorder point that will achieve a:

a. 98% service level

b. 95% service level

c. 90% service level

Problem 4: Scheduling Rules

The following jobs are waiting to  be processed at the same machine center. Jobs are logged as they arrive:

Job

Due Date

Duration (days)

A

412

12

B

418

22

C

420

34

D

429

45

E

435

48

F

451

52

In what sequence would the jobs be ranked according to the following decision rules:

1. FCFS

2. EDD

3. SPT

4. LPT

All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 265. Which decision is best and why.

Problem 5 - MRP

Period

1

2

3

4

5

6

7

8

9

10

11

12

Gross Requirements

30

20

40

10

40

60

20

80

10

90

70

10

Holding cost is $2.50/unit/week (period)

setup cost: $175

Lead time 1 week

beginning inventory 50

stockout cost=$10

1. Develop a lot for lot solution and calculate total relevant costs for the data in the above tables.

2. Develop a EOQ solution and calculate total relevant costs for the data in the above tables.

3. Develop a POQ solution and calculate total relevant costs for the data in the above tables.

4. Using the data above which is the best technique and why?

Problem 6 - Materials Requirements Planning

A manufacturing plant produces an end-item A, according to the following bill of materials:

2220_Fig.png

The MPS for the end-item A is given in table 1. The manufacturing / assembly lead times, the lot sizing rules, and the current on-hand inventory for all constituting items are given in table 2. There are scheduled receipts for item C at week 1 (100 pieces) and for item D at week 3 (80 pieces).

Table 1: MPS Quantities

MPS Quantities

1

2

3

4

5

6

7

8

9

10

Gross Requirements (Α)

-

30

-

50

-

200

-

120

180

60

Table 2: Lead times, lot sizing rules, on-hand inventory

Item

Lead Time

Lot sizing rule

On-hand inventory

A

2 weeks

Lot-for-Lot

40

B

1 week

Lot-for-Lot

20

C

2 weeks

Lot-for-Lot

20

D

3 weeks

Lot-for-Lot

300

Determine the material requirement plan (fill the following tables).

Item: A
Production Lead Time: 1 weeks Lot size rule:  Lot-for-Lot
Week No. 1 2 3 4 5 6 7 8 9 10
Gross Requirements









Adjusted Scheduled Receipts









Projected on-hand 40










Net Requirements









Planned order receipt









Planned order release









 

 

Item: B
Production Lead Time: 1 weeks Lot size rule:  Lot-for-Lot
Week No. 1 2 3 4 5 6 7 8 9 10
Gross Requirements









Adjusted Scheduled Receipts









Projected on-hand 20










Net Requirements









Planned order receipt









Planned order release









 

Item: C
Production Lead Time: 2 weeks Lot size rule:  Lot-for-Lot
Week No. 1 2 3 4 5 6 7 8 9 10
Gross Requirements









Adjusted Scheduled Receipts









Projected on-hand 20










Net Requirements









Planned order receipt









Planned order release









 

Item: D
Production Lead Time: 3 weeks Lot size rule:  Lot-for-Lot
Week No. 1 2 3 4 5 6 7 8 9 10
Gross Requirements









Adjusted Scheduled Receipts









Projected on-hand 300










Net Requirements









Planned order receipt









Planned order release









Problem 7-

Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs?

Please show all your work and provide the GANT chart.

Job

Sigma

Delta

R

40

10

S

25

30

T

50

20

U

35

35

V

55

15

Reference no: EM131207126

Questions Cloud

What is the sinusoidal expression for the current : What is the sinusoidal expression for the current? - Find the power loss in the circuit. -  How long (in seconds) does it take the current to complete six cycles?
What is the change in the volume in the graduated cylinder : What is the mass of the metal pieces alone? What is the change in the volume in the graduated cylinder? What is the volume of the metal pieces? Calculate the density of the metal.
Three parts as a cohesive final project : Create the fourth essay, combine and integrate with the other three parts as a cohesive final project that reflects the mentor's feedback. The focus on the fourth part of this project is to write a 4-5 page (300 words per page) paper in APA format..
How teaching by example influences development of ethical : Describe at least three ways a person can teach by example according to the article and provide a personal example in which you have demonstrated this concept.
Determine the optimal order quantity : Electronic Village stocks and sells a particular brand of personal computer. It costs the store $450 each time it places an order with manufacturer for the personal computers. Determine the optimal order quantity (EOQ)? What is the total annual cos..
Large video rental section or a small one in hisstore : Dick Holliday can build either a large video rental section or a small one in hisstore. He can also gather additional information (by conducting market study) orsimply do nothing. If he gathers additional information
Organization from two different organizational structures : Analyze the organizational structure of your selected organization. Differentiate the structure of the selected organization from two different organizational structures. Evaluate how organizational functions (such as marketing, finance, human reso..
Write a program to determine the rms value and period : Given a sinusoidal function, write a program to determine the rms value, frequency, and period.
Conservative and liberal actors : Race relations have once again become a debated political topic. Within the public dialogue, conservative and liberal actors have made competing claims regarding the causes of contemporary racial conflict.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd