Determine the optimal capital structure

Assignment Help Corporate Finance
Reference no: EM13289960

Bidding for a large infrastructure project - Understanding project evaluation techniques, building a project evaluation model and determining the capital structure

You are the senior portfolio manager of a major infrastructure fund, Future Infrastructure Group that is invited to participate in a Public Private Partnership transaction that involves building a major toll road connecting the Eastern Freeway with the other major toll roads. Currently, traffic from the Eastern Freeway flows into a busy arterial road causing significant congestion. The new toll road will provide an important link in the overall traffic network.  Your infrastructure fund has formed a bid consortium that includes a global road building company,a road maintenance and services company, a major Australian bank and a consulting firm.

The State Government will provide a concession agreement that allows the winning bidder (i.e. concessionaire) to collect tolls at a regulated rate over the concession period of 25 years from the date of completion of the project. In recognition of the current tight credit conditions, the State Government has agreed to provide the concessionaire with a "credit wrap" (or financial guarantee) of up a total of 30% of the project value for debt facilities to include project finance, working capital facilities, and infrastructure bonds as outlined below:

1. For an amount not exceeding 12.5 % of the project value  - 10 years

2. For an amount not exceeding 15 % of the project value - 5 years

3. For an amount not exceeding 20 % of the project value - 3 years.

The concession agreement required the bid group to contribute equity of a minimum of 30%.

It is estimated that the construction will take around two years and for the purposes of our analysis, we assume that all cash-flows during a period occur at the end of the period.

The State Government is rated AAA by global rating agency Standard &Poors and your banking partner estimates that the residual project debt is rated BBB (flat) based on S&P rating methodology.

For the purposes of this analysis you will assume a "flat term structure" of interest rates or interest rate swap curve of 10%. Your banking partner has estimated the following credit spreads over the inter-bank swap rate:

1. AAA rated debt = 0.5 %

2. BBB rated debt = 2.5%

They have offered to provide an interest rate hedge to lock in the interest rates at this level if deemed appropriate by the bid team. They would also be willing to offer credit facilities to help the project lock in any foreign exchange or commodity price risks.

Key parameters of the project as determined by your consultants are outlined below:

Project Costs:    Year 0 - Bid Costs capitalised - A$ 15 million

Year 1 - A$ 250 million

Year 2 - A$ 300 million

Hence the total project value is estimated at A$ 565 million

Interest costs on the bank loan during the construction process are capitalised and included in the total amount of A$ 565 million calculated above. Interest costs for the period of the concession agreement will be based on your capital structure and type of debt employed.

You are also provided with the following cost structures:

1. Annual Expenses other than Bank Interest costs - Estimated at A$ 25 million p.a.

2. Bank Interest Costs - As calculated by you based on debt structure employed

3. Annual Toll Receipts as outlined below:

  • Year 1 of the concession period - A$ 110 million
  • Year 2 of the concession period - A$ 150 million
  • Year 3 of the concession period - A$ 150 million
  • Year 4 of the concession period - A$ 230 million
  • Year 5 onwards to year 25 - A$ 160 million

The bid group has agreed on a internal hurdle rate of 15% for the purposes of evaluation of this project.

In bidding for the project, you are required to provide the State Government with an estimate of either how much you expect the State Government to pay you (upfront) as a subsidy or How much you are willing to pay the State Government in consideration for taking up the concession agreement.

Note to students:

1. This is a group assignment and the key focus is on ensuring you understand the financial concepts - You are required to discuss key issues among yourselves and develop a detailed excel model for calculating the project NPV.

2. Aspects of the assignment will be discussed during tutorial sessions to assist you in the learning process.

3. You can also avail the time allocated for student consultations to get a better understanding of project related issues.

 Questions

1. Based on the information provided in the case study, determine the optimal capital structure, the various financing options available and the debt maturity profile of the project. Discuss the merits and limitations of each form of financing proposed.

2. Discuss briefly some of the financial market risks associated with the project. Consider: Interest Rates, Currency and Commodity Risks if any. How can these be hedged using and what financial instruments do you propose to use.

3. Calculate all cash-flows of the project and draw a detailed cash-flow diagram for the project over 25 years.

4. Develop a detailed NPV model in excel showing Cash Inflows, Cash Outflows and NPV of the project. What is the amount that you either expect to receive or are willing to pay the State Government to win this concession. Provide your arguments.

Verified Expert

Reference no: EM13289960

Questions Cloud

How far is the man from the gate : a man is standing near a gate and a flag pole. The gate is 15 ft from the pole. If the pole is h=35 ft tall, how far is the man from the gate
Write an environmental analysis and an industry analysis : write an environmental analysis and an industry analysis
Design and build a battery charge control circuit : build a solar power system that is used for aresidential application and demonstrate in front of my class. Here are the components used in this system: Solar panel,solar charge controller, 12 V lead acid battery, DC to AC inverter,and a battery te..
What is her speed with respect to the shore : Mary needs to row her boat across a 200 m-wide river that is flowing to the east at a speed of 1.1 m/s. Mary can row with a speed of 2.4 m/s. What is her speed with respect to the shore
Determine the optimal capital structure : Based on the information provided in the case study, determine the optimal capital structure, the various financing options available and the debt maturity profile of the project. Discuss the merits and limitations of each form of financing propos..
State what is the ph of a solution that is the mixture : What is the ph of a solution that is the mixture of 0.008 M of NaOAc and 0.1 M HOAc? (Ka HOAc= 1.8 x 10^-5)
Create an internet marketing plan : Net-a-porter.com and create an Internet marketing plan
What is the speedometer reading of the car : A 60-kg student traveling in a car with a constant velocity has a kinetic energy of 1.2 X 104 J. What is the speedometer reading of the car
What is the amount ford owe in taxes next year : Without the new SUV, Ford expects to earn pre-tax income of $80 million from operations next year. Ford pays a 30% tax rate on its pre-tax income. What is the amount Ford owe in taxes next year with the launch of the new SUV?

Reviews

Write a Review

Corporate Finance Questions & Answers

  Calculate each projects payback period-net present value

Calculate each projects payback period, net present value (NPV) and which project or projects is financially acceptable? Explain your answer.

  What is your net new financing needed for next year

Your non-debt liabilities such as accounts payable are forecasted to increase by $10,000. What is your net new financing needed for next year?

  What is the minimum amount of robin salary

Robin is working overseas on a temporary assignment beginning on March 1 of this year through January 31 of next year. Her salary is $10,000 per month while overseas, but only $8,000 per month for January and February of this year.

  Calculate the expected npv & coefficient of variation

Trail Guides, Corporation, is currently evaluating 2 mutually exclusive investment. After doing a scenario analysis & applying probabilities to every scenario;

  Identify key inflection points in the companys stock price

Select a puplicly listed company of your choosing. Identify key inflection points in the company's stock price going back three years. Analysis and discuss the impact of the various events which lead to these stock price movements.

  Highest to lowest returns and risk

Which of the following lists correctly ranks investments from highest to lowest returns and risk (thus, the highest risk security should be shown first, the lowest risk securities shown last)?

  Preparing financial statements

Preparing Financial Statements,  List and explain investors' motivation for investing in stocks, bonds, preferred shares, and convertibles based on the characteristics of each of these financial vehicles from the risk and income perspective of invest..

  Calculate the firms weighted average cost of capital

Calculate the firm's weighted average cost of capital and what is Nealon's cost of equity capital when new shares are sold, and what is the weighted average cost of the added funds involved in the issuance of new shares?

  Questions based on return on equity

How much must the assets be reduced to bring the TATO to the industry average and questions based on Return on equity

  Taxation on investments

Investor purchase 100 shares in a mutual fund on January 1 2009 for $50 each the fund receive dividends $2 and $3 per share during the 2009 and 2010.

  Is garbage collection a public good

If it is a private good and not a public good, why is garbage collection so often provided directly by government and not the private sector?

  Questions related to stock exchange

Theory questions regarding stock exchange - Is the control issue likely to be of more importance to stockholders of publicly owned or closely held firms? Explain

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd