Determine the maximum capacity of the current production

Assignment Help Operation Management
Reference no: EM131431876

Modelling & Simulation for Operations Management Assignment case study for Witness modelling and process improvement

Drive shaft manufacture

You have been employed as a member of a production improvement task force for a Drive Shaft Manufacturing Company (DSMC). DSMC has been experiencing a severe backlog in sales orders due to antiquated machinery and poor production planning. The Company has just received an unprecedented contract to supply 450 drive shafts by the process given below. However, finances at present are tight and only £250,000 can be invested. Some of the order can be sub-contracted. Your task is to determine the maximum capacity of the current production line after the investment of the £250,000 hence how many parts must be made by the sub-contractor. The cost list of potential capital improvements is given on next page.

The current output of the line averages 180 shafts on the two 38-hour shift system.

Process:

The drive shaft manufacture starts with a bar of 0.3 metres long that is cut into three parts (blocks). The operations are as follows (one machine at each operation unless stated otherwise):

1. The bar arrives based on vendor's supply schedule in lots of 3, every 30 minutes. The bar stock buffer can hold only 10 bars.

2. In the Saw machine, the time to cut the bar into 3 blocks is 6 minutes. Blade A is replaced every 40 operation and blade B every 30 operations. Set-up time is uniformly distributed between 10 and 15 minutes. Time between failures is NEGEXP with mean of 100, and the repair time follows triangular distribution with min 10, mode 25 and max 30. An operator is required to run this machine.

3. After sawing the blocks go to a Fixed conveyor with index time = 0.25 min, length 20 parts.

4. Once sawed the blocks must be coated for protection. The Coating machine takes 6 parts per cycle and has a cycle time of 60 minutes. Every 10 cycles, the machine is set-up for 5 minutes.

5. Once coated, the blocks are placed in a staging buffer of capacity 10 part, adjacent to the Inspector.

6. The Inspector draws from the staging area one block at a time and checks the quality of the block's coating. The cycle time = 20 min, set-up = 1min per part. If the coating is bad, the Inspector puts the rejected block into a Rework buffer of capacity 10. The reject rate is 20%, and rejects are returned to be recoated.

7. Parts are cured on an individual basis on a chain conveyor (Hardener) of capacity 10 parts through a furnace, a process on a first in first out basis. Heat-treat time is 60 min.

8. The hardened parts go for Gear cutting: cycle time 2 minutes + 1 minute load and unload that is manual, 2 machines, tool change every 100 parts for 10 minutes. Breakdowns mean time to failure 5000 minutes NegExp, repair time normal mean 80 minutes σ = 10. One operator runs two machines and changes cutter.

9. Four parts are Loaded into a special fixture in 4 minutes before entering for grinding; 10 fixtures are available in the system and are stored in a Fixture buffer if not used.

10. The 4 parts and the fixture are loaded to the Grinders (2 machines): cycle times M/c 1 = 35 min, M/c 2 = 40 min; Time between failures is normal distribution with mean = 75 min, SD = 15. The repair time is NEGEXP of mean 15 min and is repaired by the Saw operator.

11. Once ground, the fixture is Unloaded in 4 minutes. The fixture returns to the Fixture buffer and the parts go to two buffers of capacity 10 parts each.

12. The parts are then cleaned in the Wash machine, a multi stage machine with 5 stations, 1 part per station, cycle time = 15. Time between failures NEGEXP of mean 120 min, the repair follows Erlang distribution with mean = 20 min, K = 3. The machine is set-up every 100 operations, time 5 min. Set-up and repair are carried out by the Saw operator.

13. The Plating process follows and takes 36 parts per cycle, cycle time 36 minutes, buffers on machine 72 parts both before and after process. Due to chemical change on Monday morning, 4 hours are lost. An operator is required.

14. The parts are then washed with a Wash machine identical to 12.

15. The finished parts are Packed in Pack cycle time of 1.25 min. Packed into flat pack boxes one drive shaft per box. Boxes arrive in batches of 1000, frequency of deliveries to be determined by model. One operator required.

16. The boxes are finally shipped.

Attachment:- Assignment File.rar

Reference no: EM131431876

Questions Cloud

Describe the promotional pricing strategies : Read the short HBR article - The "Maximize Profits" Trap in Decision Making and Describe the promotional pricing strategy(ies) that are most appropriate for your GOMC Client: TONY TEJAS SALSA
Do you agree with fasb that the direct method is preferred : What are the differences between the indirect and direct methods of preparing the statement of cash flows? Do you agree with the FASB that the direct method is preferred? Why, or why not?
Explain what the cash flow ratios indicate about the company : Demonstrate your calculations in your post, and explain what the cash flow ratios indicate about the company. Do not choose a company previously chosen by one of your classmates.
What are the advantages of the twenty-year mortgages : You must now choose between a 20-year mortgage and a 30-year mortgage. What are the advantages and disadvantages of the 30-year and the 20-year mortgages?
Determine the maximum capacity of the current production : MOD002610 Modelling & Simulation for Operations Management Assignment case study for Witness modelling and process improvement. Your task is to determine the maximum capacity of the current production line after the investment of the £250,000 hence..
What does the standard error indicate : What does the standard error indicate about how accurate the sample standard deviation is as an estimate of the population standard deviation?
Briefly discuss the types of ethical issues : Briefly discuss the types of ethical issues involved in computerized accounting information systems and how organizations can encourage their employees to act ethically.
What is the exact sampling distribution of the sample mean : Write a careful description comparing the three bootstrap distributions and also comparing them with the exact sampling distribution. What are the effects of increasing the sample size?
How non normality of population affect bootstrap : Explain what you have observed based on what you know about the sampling distribution of x‾ and the way in which bootstrap distributions mimic the sampling distribution.

Reviews

len1431876

3/18/2017 3:51:11 AM

Hello, would you be able to do this assignment? This assignment has to be done in Witness Horizon 10 software. Note: Please present the process in a pseudo format before building the model in Witness.

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd