Determine the market clearing price

Assignment Help Electrical Engineering
Reference no: EM132331590

Question 1

The MATLAB file psa9p12.m or psay11_a2q1.m or other power flow software should be used for this question.

2246_LOADS at peak time.jpg

LOADS (at peak time)

BUS 2: 60 MW + 12 MVAr

BUS 3: 60 MW + 12 MVAr

BUS 4: 120 MW + 0 MVAr

Generation

Active power from G2 = 120 MW (at peak time); Bus 1 is the swing bus

Bus voltages

Voltages at bus 1 and bus 5 fixed at 1 pu by the AVRs (automatic voltage regulator) of the generators.

Bus 2, Bus 3 and Bus 4 are load buses (or PQ buses or bus type 1).

Transformers Ratings

Transformer rating (both) : 180 MVA Tap position fixed at nominal value Line Ratings:
All lines: 480 A

Generator Ratings:

For each generator, Active Power Limit = 150 MW; MVA limit = 180 MVA

System data (common MVA base of 200)

Series impedance for T1 = 0.02+ j0.12 pu Series impedance for T2 = 0.02+ j0.10 pu
Per phase series impedance for line 1 = (0.05 + j 0.125) pu = 12.1+ j 30.3 Ω Per phase series impedance for line 2 = (0.1 + j 0.25) pu = 24.2 + j 60.6 Ω Per phase susceptance for line 1 = 0.0303 pu = 125 μS
Per phase susceptance for line 2 = 0.0605 pu = 250 μS

(a) Determine the bus voltages in pu at system peak. Do you detect any problems?

(b) Determine the required level of VAR generation at bus 4 if voltage at that bus is to be brought up to 1 pu at system peak load. (Assume there is a synchronous condenser available at bus 4).

(c) The geographical distance between bus 2 and bus 4 is the same as the distance between bus 3 and bus 4. A new transmission line (line 3) will be installed between bus 3 and bus 4. It will have the same electrical characteristics as line 2. State one major operational benefit that will result from line 3. Justify and illustrate by appropriate quantitative analysis.

Question 2

Use a common base MVA of 100.

458_System impedance.jpg

Table 1: System impedance

 

Plant

 

Rated voltage kV

 

Rated MVA

 

X+

pu

 

X-

pu

 

pu

 

G1

R1= 0.5 Ω

 

20

 

200

 

0.25

 

0.15

 

0.08

G2

R2=0.5 Ω

 

25

 

300

 

0.2

 

0.15

 

0.1

 

T1

 

20/220

 

350

 

0.10

 

0.10

 

0.10

 

T2

 

25/220

 

350

 

0.10

 

0.10

 

0.10

 

T3

 

220/66/11

 

200

0.04

per winding

0.04

per winding

0.04

per winding

 

L1 80 km

 

220

 

n/a

 

j 0.5 Ω/km

 

j 0.5 Ω/km

 

j 1.1 Ω/km

 

L2 100 km

 

220

 

n/a

 

j 0.5 Ω/km

 

j 0.5 Ω/km

 

j 1.1 Ω/km

 

L3 120 km

 

220

 

n/a

 

j 0.5 Ω/km

 

j 0.5 Ω/km

 

j 1.1 Ω/km

Assumed prefault conditions: system unloaded with all bus voltage = 1 pu

(a) Draw the positive, negative, and zero sequence networks for the system. Include all impedance values.

(b) A three phase bolted fault occurs on line 2 at a point equidistant between bus 1 and bus 3.

Calculate the following currents (in amperes): The Fault current
Line current for Generator 1 Line current for Generator 2

(c) Assume that a single line to ground bolted fault occurs at bus 3. Using the networks from (a), calculate (in ampere) the resulting fault current.

Question 3

Repeat example 13.9 of your textbook with the same loading limits and coefficients as given in table 13.5 and start-up cost of $3000 and shut-down cost of $1500 respectively. However the loading given in figure 13.11 is now changed to:

Stage Number

1

(0-4 am)

2

(4-8am)

3

(8-12 pm)

4

(12-4pm)

5

(4-8pm)

6

(8-12am)

Load (MW)

 

900

 

1200

 

1400

 

1600

 

1200

 

900

Question 4

Repeat question 3 above for the case of a competitive electrical energy market set to supply electricity for a community on a relatively small island with an electricity network not connected to any external networks. Transmission losses may be neglected. Each one of the four generators is owned by a separate private company which is a market participant. The competitive electricity market consists of (a) a capacity market (b) a day ahead market and (c) a frequency control market. The capacity market may be considered settled and is not relevant to this question. Generators may simultaneously participate in both the frequency control market and the day ahead market. However if a generator is providing frequency control services then its set point should be no lower 25 MW above its minimum loading limit and no higher than 25 MW below its maximum loading limit. This is to allow control of frequency under normal fluctuations of load. Generators providing frequency control services are paid a fixed amount of $5000 for every dispatch period of 4 hours. You may assume that any participant is paid the fixed amount of $5000 if their generator is on- line during any one of the 4-hour dispatch period. However here the principle is being applied to a four hour dispatch period.

For simplicity, assume that each participant's bid is the same for all of the six dispatch interval shown above.

(a) If you were the owner of generator unit number one, what as participant in the day ahead market would be your bid? Explain the basis of your bid.

(b) Assuming reasonable bids from the other three participants, determine the market clearing price for the six dispatch intervals.

(c) Calculate total revenue and profits for each participant for the 24-hour period.

Note: Want the solution of all problems except Question 2.

Reference no: EM132331590

Questions Cloud

Computing environment understand the file system management : Please help me understanding the answer, "Given an Operating System in a computing environment understand the file system management, memory management
The pesticide works to kill the targeted organism : Identify and describe which of the four cornerstones of xenobiotic pharmacokinetics are affected in the way the pesticide works to kill the targeted organism.
Prepare the statement of cash flows of metagrobolize : Prepare the statement of cash flows of Metagrobolize for the year ended December 31, 2018. Present cash flows from operating activities by the direct method.
Explain the old the new and the improved : Several protocols have been resurrected as 'new and improved' technologies. Research one such protocol/technology. Explain the old, the new, and the improved.
Determine the market clearing price : ELE3807 - Power Systems Analysis - University of Southern Queensland - Calculate total revenue and profits for each participant for the 24-hour period
Guidelines for designing for the user : State at least three guidelines for designing for the user, and explain how following these guidelines will help developers create user-centered site?
Environments is one which should be symbiotic : Thesis--One could posit, the relation between humans and their environments is one which should be symbiotic.
Identify the exposure pathway of your chosen chemical : Identify how the individual was exposed to the chemical. Identify exposure pathway of your chosen chemical. What organ systems were affected by chemical?
Analyze the acute and chronic effects of the toxicant : Explain the normal function of the system and what makes it susceptible to toxicity. Analyze the acute and/or chronic effects of the toxicant.

Reviews

len2331590

7/2/2019 12:09:22 AM

I want the solution of all problems except problem number 2. Please go through it and let me know, all the data is sufficient for you in order to solve the problem?

Write a Review

Electrical Engineering Questions & Answers

  Lithium ion battery technology

The paper includes Lithium ion battery technology with its advantages and disadvantages. The paper discusses about the Lithium air battery in which detailed reactions of Lithium with air including nonaqueous as well as aqueous are given.

  Power transformers and tariffs

Construction of different types of power transformer, significant energy savings

  Paper on orthogonal frequency-division multiplexing

This document is shown a paper on Orthogonal frequency-division multiplexing with advantages, disadvantages and uses.

  Function of the hmi in a scada system

This assignment contains electronics engineering questions like State the commonly found components of a SCADA (Supervisory control and data acquisition) system. and decribe the function of the HMI in a SCADA system.

  Resultant waveform of the odd harmonic series

Prepare an Excel graph showing the individual components and summated resultant waveform of the odd harmonic series resulting in an approximate square wave.

  Explain scada system

Explain the function of the HMI in a SCADA system.

  Design a 2-digit 24 second shot-clock

Design a 2-digit 24 second "shot-clock" countdown timer with pushbutton controller.

  Model a discrete-time system

To understand di erent signal models To be able to model a discrete-time system and design simple signal processing algorithms.

  Draw a relay construction diagram

Draw a relay construction diagram and briefly explain the operation of a relay.

  Frequency division multiplexing

Write a short technical report on Frequency Division Multiplexing

  Impact of electron energy

Briefly discuss the impact of electron energy, electron current and target on the Bremsstrahlung generated.

  Traffic light controller

The schematic of the traffic light controller

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd