Question - Wolseley's dilemma of Traditional Costing versus Activity Based Costing Wolseley Manufacturing Corporation manufactures various electronics products and follows a traditional (job-order) costing system in which it applies manufacturing overhead to its products using a predetermined overhead rate based on direct labour-hours (DLHs). The company has two products, C18R and G19R, about which it has provided the following data:

 

C18R

G19R

Direct materials per unit

$10.20

$50.50

Direct labour per unit

$8.40

$25.20

Direct labour hours per unit

0.40

1.20

Annual production

30,000

10,000

The company's estimated total manufacturing overhead for the year is $1,464,480 and the company's estimated total direct labour-hours for the year is 24,000.

The company is considering using a variation of activity-based costing to determine its unit product costs for external reports. Data for this proposed activity-based costing system appear below:

Activities and Activity Measures

Estimated Overhead Cost

Supporting direct labour (DLHs) $552,000

Setting up machines (setups) 132,480

Parts administration (part types) 780,000

Total $1,464,480

Activities

C18R

G19R

Total

Supporting direct labour

12,000

12,000

24,000

Setting up machines

864

240

1,104

Part administration

600

960

1,560

Mike, who is the controller of the Company, is currently overseeing the project to switch from traditional costing to Activity-Based costing. He is in a meeting with the Cost Accountant of the company. The Controller goes over the data and makes the following comments:

"Activity-Based Costing is a revelation in the modern-day world of manufacturing Industry. If we are correctly able to categorize the various nature of work into essential levels, then we can dramatically trace the precise nature of the overheard activity."

Jacob, the Cost Accountant, quips, "how can we classify those levels of activities? Do we have some mechanism to identify them?"

Mike responds, "Yes! We do."

Jacob then laments the pitfalls of the job order costing system, "The production report will be out soon and usually, the allocation bases (including overhead allocations in job-order costing systems) are not entirely accurate." Mike, with a pause, "That is exactly why we may eventually need to switch to the Activity-Based costing though it is comparatively difficult to implement with the cost and operations limitations involved in it."

Jacob adds, "Another consideration to evaluate is the relationship between the cost of maximum (budgeted) capacity and idle capacity, since the company is likely to operate at maximum capacities during the time of peak demand. Moreover, our long-term goals of stable cost predictions and waste minimizations should also be kept in mind."

"Alright! Let us calculate and analyze the quantitative and qualitative aspects of the data and other factors we have discussed in the meeting today and prepare the preliminary report for the CEO by this weekend." Mike with the final comments!

Required -

a. Determine the manufacturing overhead cost per unit of each of the company's two products under the traditional costing system.

b. Determine the manufacturing overhead cost per unit of each of the company's two products under activity-based costing system.

c. Compare the results in part a and b under both costing systems and specify the differences in both systems.

d. What is the significance of the Activity Costing System that Mike is referring to?

e. How is ABC system different from traditional costing system?

f. The use of which activity level, budgeted (same as expected) or maximum capacity, is consistent with ABC? Explain.

g. How might the use of ABC based on maximum capacity activity level enhance a firm's ability to compete on price? Explain.

h. If you were to recommend one of the costing systems for Wolseley Inc., which one would you pick and why?

Reference no: EM132855403

Questions Cloud

Predictive analytics and leadership : The authors of the study conclude that "The consistency in identified challenges between Weak BI Adopters and Weak AA Adopters tells two stories
Explain the difference in opportunity cost : What is the opportunity cost of producing an additional shoe in East Stan, given the number of bikes that were abandoned?
Calculate confidence interval for males and females : What impact are the different means having on the intervals and what impact are the different standard deviations having?
Does the west continue to dominate global news flow : Asian values in journalism and its impact across the Asia-Pacific region. Does the West continue to dominate global news flow?
Determine the manufacturing overhead cost per unit : Determine the manufacturing overhead cost per unit of each of the company's two products under the traditional costing system
Compute the expected length of the arc : Choose, at random, three points on the circle x 2 + y 2 = 1. Interpret them as cuts that divide the circle into three arcs.
Determine timeline of the grant as well as activity timeline : Determine the timeline of the grant as well as your activity timeline and management plan to ensure you have covered all the nuances of project work.
Find the indicated probability : Find the indicated probability. (Enter a number. Round your answer to four decimal places.
What do see as benefits and challenges of review process : What do see as benefits and challenges of review process? What happens once a proposal is submitted? How are funded proposals selected?

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd