Determine the length of the hydraulic jump and energy loss

Assignment Help Civil Engineering
Reference no: EM13298948

A spillway carries a discharge of 22.5 m^3/sec with the outlet velocity of 15 m/sec at a depth of 0.2m. Select an adequate USBR stilling basin and determine the sequent depth, the length of the hydraulic jump and energy loss.

Reference no: EM13298948

Questions Cloud

Local performers are gradually loosing in the competition : Local performers are gradually loosing in the competition with recognized international bands, and Serida’s income decreases to $50 while prices are the same as before. What is the equation of this new budget line? How does it compare to the budget l..
Determine itc percentage change in earnings : Suppose that ITC's degree of combined leverage (DCL) is 3.00 at a sales volume of $9 million. Determine ITC's percentage change in earnings per share (EPS) if forecasted sales increase by 20 percent to $10,800,000.
Determine the depth that will result upstream during design : The design discharge is 9.5 m^3/sec and the inlet will be submerged but not the outlet. Determine the depth that will result upstream (above the invert) during the design flood event.
What is the firms fixed cost : Suppose that the total short-run cost function of a firm is given by TC = 200 + 20Q, where TC is the total cost and Q is the total quantity of output.
Determine the length of the hydraulic jump and energy loss : A spillway carries a discharge of 22.5 m^3/sec with the outlet velocity of 15 m/sec at a depth of 0.2m. Select an adequate USBR stilling basin and determine the sequent depth, the length of the hydraulic jump and energy loss.
Explain solvents in order of increasing polarity and acetone : Rank the following solvents in order of increasing polarity: Acetone, Petroleum ether, methanol, ethanol, dichloromethane
Find elevation difference in siphon crown nd downstream pool : The siphon crown is 1.2m above the water surface elevation of the reservoir and a length of 10m away from the siphon entrance. If the siphon diameter is 30 cm, the friction factor is 0.2, and the head loss coefficients are 0.2 inlet and 0.1 exit,
What is the value of the stock to an investor : An Allied Northern preferred stock pays a $3.84 annual dividend. What is the value of the stock to an investor who requires a 9.5% return?
Suppose that starplex decides to implement third degree : Suppose that Starplex decides to implement third degree price dis-crimination. How many tickets w ll be purchased by college students? What price should Starplex charge college students? [Hint: carry youranswer out to two places past the decimal

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate the amount of water to be added per cubic meter

An undisturbed soil sample has a total unit weight of 19.4 kN/m3, a dry unit weight of 16.9 kN/m3, and a specific gravity of soil solids (Gs) of 2.69. If the sample could be saturated without changing its porosity, calculate the amount of water (i..

  Calculate the height above the waterline

A fully loaded, ocean going container ship is just stable about its longitudinal axis (roll). The ship has a total weight of 155,000 tons, length = 1,600 feet and a beam = 150 feet (assume that it is the shape of a rectangular box). Calculate the ..

  Determine what is the effluent bod concentration

An activated sludge tank, 30 x 30 x 200 ft, is designed as a plug-flow reactor, with an influent BOD of 200 mg/L and a flow rate of 1 million gallons per day. a. If BOD removal is first-order reaction, and the rate constant is 2.5 days^-1, what is ..

  How long will it take for primary consolidation settlement

A compressible 12-ft clay layer beneath a building is overlain by a stratum of sand and gravel and underlain by impermeable bedrock. The total expected primary consolidation settlement of the compressible clay layer due to the building load is 4.6..

  Estimate extent of laminar boundary layer flow along wing

An airplane flies at a speed of 360 mph at an altitude of 5000 ft. If the boundary layers on the wing surfaces behave as those on a flat plate, estimate the extent of laminar boundary layer flow along the wing in feet.

  Sketch a streamline pathline and streakline

Sketch a streamline, pathline, and streakline, For a given flow the velocity from time t=0 to t=5s was u=2 m/s, v=0. Then from t=5s to t=10s the velocity was u=+3 m/s, v=-4 m/s. A dye streak was started at t=0

  Define the term coefficient of permeability

How would you define the coefficient of permeability? Give typical values of the coefficient for: a) fresh cement pastes; b) hardened cement pastes; c) commonly used aggregates;

  Average shearing stress

Two strips of a plastics material are bonded together as shown. The average shearing stress in the glue must be limited to 1000 kpa.

  Travel of two particles problem

Two particles start from the same point along the same straight line and at the same instant. The first particle travels with a constant velocity v and the second with a constant acceleration.

  Determine flow rate of water that will cause a pressure drop

Determine the flow rate of water (20 degrees celcius) that will cause a pressure drop of 17250 N/m^2 in 350m of horizontal, cast-iron pipe (d=60cm). assume minor losses are negligibe

  Absolute pressure of the carbon dioxide in the can

The circular top of a can has a radius of .0320m. the pull-tab has an area of 3.8x10^-4 m^2. The absolute pressure of the carbon dioxide in the can is 1.40x10^5Pa. find the force that these gas generates on the top of a can?

  Commercial management in civil engineering

Devise a appropriate management system that you as a commercial manager for the contractor would recommend to the project team for use on a construction or building contract.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd