Reference no: EM132710088
Question 1 - Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows:
Direct material of 5.50 yards at $5.50 per yard
Direct labor of 2.00 hours at $20.00 per hour
Overhead applied per sleeping bag at $17.00
In the month of April, the company actually produced 5,200 sleeping bags using 27,300 yards of material at a cost of $5.70 per yard. The labor used was 11,700 hours at an average rate of $20.50 per hour. The actual overhead spending was $96,200.
Determine the total materials variance and round to the nearest whole dollar. Enter a favorable variance as a negative number. Enter an unfavorable variance as a positive number.
Question 2 - Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows:
Direct material of 6.00 yards at $5.50 per yard
Direct labor of 3.00 hours at $16.00 per hour
Overhead applied per sleeping bag at $17.00
In the month of April, the company actually produced 5,200 sleeping bags using 27,300 yards of material at a cost of $5.30 per yard. The labor used was 11,700 hours at an average rate of $19.50 per hour. The actual overhead spending was $96,200.
Determine the labor rate variance and round to the nearest whole dollar. Enter a favorable variance as a negative number. Enter an unfavorable variance as a positive number.