Reference no: EM132315459
Question :
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building:
Title insurance
|
$22,000
|
Legal fees for drawing the contract
|
8,000
|
Pro-rated property taxes for the period after acquisition
|
42,000
|
State transfer fees
|
4,600
|
An independent appraisal estimated the fair values of the land and building, if purchased separately, at $4 and $1 million, respectively. Shortly after acquisition, Samtech spent $88,000 to construct a parking lot and $46,000 for landscaping.
Required:
1. Determine the initial valuation of each asset Samtech acquired in these transactions.
2. Determine the initial valuation of each asset, assuming that immediately after acquisition, Samtech demolished the building. Demolition costs were $310,000 and the salvaged materials were sold for $9,000. In addition, Samtech spent $85,000 clearing and grading the land in preparation for the construction of a new building.
Required 1
Determine the initial valuation of each asset Samtech acquired in these transactions. (Enter your answers in whole dollars.)
Initial Valuation
Land
Building
Land improvements
Required 2
Determine the initial valuation of each asset, assuming that immediately after acquisition, Samtech demolished the building. Demolition costs were $310,000 and the salvaged materials were sold for $9,000. In addition, Samtech spent $85,000 clearing and grading the land in preparation for the construction of a new building. (Enter your answers in whole dollars.)
Initial Valuation
Land
Building
Land improvements