Cost and Schedule Control

Assignment 1:

You are managing a small project which includes building a boundary wall for a square plot. The wall is exactly the same on each of the four sides. Assumption: time and costs for each side will be same. Estimated duration of the project is 8 days to complete and the budget, including contingency reserves for risks is $12,000.

At the end of 4 days, you need to report the progress of the project. Are asked to prepare ayou decide to use the Earned Value calculation in order to determine the health of the project. The team reports that end of day 4, total costs incurred are $5,500. And 30% of the project is completed.

Calculate
SV, CV, SPI, CPI. What do these indicate about the status of the project? Interpret your results in terms of schedule and cost progress.
Suggest one best action corrective (if applicable) and justify your recommendations.

QUALITY ASSURANCE AND AUDIT

Assignment 2:

Refer to the Self Assessment form on Quality Assurance and Audit, Chapter 1 Slide no. 11, Category4 Measurement, Analysis and Knowledge Management.

For each of the points from 4a to 4f, if you have marked Strongly Agree / Agree discuss the existing process within your organization to explain how it is done.

E.g. for 4a Discuss how exactly is the quality of your work measured. Write down the Key Performance Indicators used.

If you have marked Neither Agree nor disagree / Disagree / Strongly Disagree, suggest how the same could be achieved.

e.g. for 4a Discuss how exactly you think the quality of your work can be measured. Write down the Key Performance Indicators which you can use.

This needs to be done for all points from 4a to 4f.

Attachment:- Activity.rar

Reference no: EM132068241

Questions Cloud

Describe one of personality traits : Describe one of your personality traits that you believe to be highly heritable and another trait that seems to be much less so.
Difference between money market and capital market : Describe the major advantages and disadvantages of three mains forms of business organizations: the proprietorship, the partnership and the corporation.
Develop positioning statement for social marketing project : Using the template on page 242 and 510 develop a positioning statement for your social marketing project.
What is the banks total risk-weighted assets : What is the bank's "adjusted" risk-weighted assets used in the calculation of the capital ratios?What is the bank's CET1 risk-based capital ratio?
Determine the health of the project : COST and SCHEDULE CONTROL - What do these indicate about the status of the project? Interpret your results in terms of schedule and cost progress.
Team to showcase the business idea : It allows your group/team to showcase the business idea identified by the group as the "best one" during workshops earlier in the unit.
Team to showcase the business idea : It allows your group/team to showcase the business idea identified by the group as the "best one" during workshops earlier in the unit.
Give the transition probabilities for the markov chain : A component in a stystem is placed into service, where it operates until its failuer, whereupon it is replaced at the end of the period with a new component
Example of one possibility : You do not need to discuss all alternatives; rather give an example of one possibility and discuss the advantages, disadvantage and limitations.

Reviews

Write a Review

Supply Chain Management Questions & Answers

  Supply chain network design for cwc

This assignment explain the supply chain management process of cwc. What is the current annual supply chain cost?

  Criteria when making new location decisions

Identify a number of the typical criteria used when making new location decisions

  Draw the project network

Determine the mean critical path for Brent's job search process. What is the variance of the project duration?

  Compare and contrast economic - market, and relevancy

Please compare and contrast economic, market, and relevancy value.

  Brushing up on inventory control

Health system in Pennsylvania

  Supply chain strategy

Supply chain strategy

  What is the economic order quantity for fans in units

Nittany Fans of Lewistown, Pennsylvania, is a distributor of industrial fans used in plants, warehouses, and other industrial facilities.

  What factors reduce the capacity of the organization

What factors reduce the capacity of the organization to get its objectives?

  What is the total annual cost

What is the total annual cost

  Supply chain management questions

Briefly define the following two supply chain metrics: (i) inventory turnover ratio and (ii) supply chain velocity.

  Explain the supply chain management concept

Explain the supply chain management concept, Differentiate between public and private sector organisations in terms of their supply chain objectives and strategies

  How warehouses can add value in the supply chain

How warehouses can add value in the supply chain

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd