Reference no: EM132633704
The Zalucki Company plans to use ABC method to determine its product costs. It presently uses a single plant wide factory overhead rate for allocating overhead to products, based on direct labor hours. The total factory overhead cost is as follows:
Department Factory Overhead
Production Support 1,225,000
Production (FOH only) 175,000
Total Cost 1,400,000
The company determined that it performed four major activities in the Production Support Department. These activities, along with their budgeted costs, are as follows:
Production Support Activities Budgeted Costs
Setup 428,750
Production Control 245,000
Quality Control 183,750
Materials Management 367,500
Total 1,225,000
Zalucki Company estimated the following activity base usage and units produced for each of its three products:
TV Computer Cellphone Total
Number of Units 10,000 2,000 50,000 62,000
Direct Labor Hours 25,000 10,000 140,000 175,000
Setups 80 40 5 125
Production Orders 80 40 5 125
Inspections 35 40 0 75
Material Requisition 320 400 30 750
REQUIRED:
Problem 1. Determine the FOH for TV, Computer and Cellphone under the single plant wide factory overhead rate method. Use direct labor hours as the activity base
Problem 2. Determine the factory overhead costs for TV, Computer and Cellphone under activity- based costing
Problem 3. Which method provides more accurate product costing? Why?