McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable.
A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table.
Following are the activities that are required to install the carpets in the offices:
· Activity 1: Measure office room dimensions
· Activity 2: Estimate cost
· Activity 3: Material requisition
· Activity 4: Workforce requisition
· Activity 5: Special tool requisition
· Activity 6: Installation
· Activity 7: Inspection and customer acceptance
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities
|
OT
|
MT
|
PT
|
Activity 1
|
4
|
6
|
14
|
Activity 2
|
5
|
12
|
16
|
Activity 3
|
7
|
15
|
23
|
Activity 4
|
13
|
16
|
28
|
Activity 5
|
17
|
20
|
35
|
Activity 6
|
20
|
32
|
50
|
Activity 7
|
5
|
6
|
13
|
You must also do the following:
· Determine the expected completion time and the variance for each activity
· Determine the total project completion time and the critical path for the project
· Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
· What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
· Define project management and the necessary requirements.
· Analyze implications of changes in project scheduling.
· Evaluate application of project management techniques in terms of the firm's business operational goals and requirements.
Access the early american wars worksheet
: Access the "Early American Wars" worksheet. Complete the worksheet by answering each prompt, addressing one of the following wars: the French and Indian War.
|
Identify the management issues that are portrayed in case
: Management Case:. Developing Global Teams to Meet 21st Century Challenges at W.L. Gore & Associates.
|
Critical ratio-optimal order quantity
: What is the underage cost, the overage cost, the critical ratio, and the optimal order quantity?
|
Responsibility for accounting and financial compliance lie
: Where should the responsibility for accounting and financial compliance lie – in the department or at the corporate level?
|
Determine the expected completion time and the variance.
: Determine the expected completion time and the variance for each activity. Determine the total project completion time and the critical path for the project.
|
Besides interest rates and maturity of the bond
: What are at least two risks (besides interest rates and maturity of the bond) that you believe affect the yield curve of bonds.
|
Justify investment decisions based on health of the industry
: Assume you are a hedge fund manager or an investment manager investing for your clients' funds in stocks, bonds, futures, options, foreign currencies.
|
Identify the elements of data backup planning
: Define, describe and identify the elements of (a) good Data Backup Planning, (b) good Disaster Recovery Planning, and (c) good Business Continuity Planning
|
Use to monitor and control revenues and expenses
: What financial reports does your department use to monitor and control revenues and expenses?
|