McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:
Activity 1: Measure office room dimensions
Activity 2: Estimate cost
Activity 3: Material requisition
Activity 4: Workforce requisition
Activity 5: Special tool requisition
Activity 6: Installation
Activity 7: Inspection and customer acceptance
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities
|
OT
|
MT
|
PT
|
Activity 1
|
4
|
6
|
14
|
Activity 2
|
5
|
12
|
16
|
Activity 3
|
7
|
15
|
23
|
Activity 4
|
13
|
16
|
28
|
Activity 5
|
17
|
20
|
35
|
Activity 6
|
20
|
32
|
50
|
Activity 7
|
5
|
6
|
13
|
You must also do the following:
Determine the expected completion time and the variance for each activity
Determine the total project completion time and the critical path for the project
Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
Define project management and the necessary requirements.
Analyze implications of changes in project scheduling.
Evaluate application of project management techniques in terms of the firm's business operational goals and requirement.
Using an aggregate demand and supply diagram
: Using an aggregate demand and supply diagram, explain how each of the following scenarios affects the equilibrium price level and aggregate output. Consider first the short-run, then the long-run equilibrium for each scenario.
|
Describe a time when you had a negative service experience
: Describe a time when you had a negative service experience. What could the company have done differently to keep you in the zone of tolerance
|
Maximum inflation from circumference data
: Calculate balloon volume for each balloon at maximum inflation from circumference data. (You will have to assume that the balloon was a perfect sphere.) To calculate balloon volume, first find the radius (in cm) of the balloon by using the formula C ..
|
Think about an advertisement either a strongly positive
: Think about an advertisement (in any medium) that had either a strongly positive or strongly negative effect on your attitude toward the product being advertised or the advertiser itself. Why did the ad have this effect? If you responded positively t..
|
Determine the expected completion time
: Determine the expected completion time and the variance for each activity and Determine the total project completion time and the critical path for the project
|
Explain the iberian factor in early latin america
: The course of events in the Western Hemisphere over the centuries following contact demonstrates that the Iberian factor in early Latin America was uniform and the result of long term processes.
|
Marketing plan - pricing and distribution strategy
: Determine the key strengths and weaknesses of your company, as well as both the primary opportunities and threats that it faces within its industry - Determine the key strengths and weaknesses of your company, as well as both the primary opportuni..
|
Define deterministic stochastic multiperiod and multiechelon
: Define deterministic, stochastic, multiperiod, and multiechelon. Which methodology should be used by SBS and by MLD
|
Western county bank is a small community bank
: Western County Bank is a small community bank that makes a modest profit by providing small business and personal loans to customers within the county and surrounding areas.For this task you will be using the attached "Western County Bank Scenario" t..
|