McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:
Activity 1: Measure office room dimensions
Activity 2: Estimate cost
Activity 3: Material requisition
Activity 4: Workforce requisition
Activity 5: Special tool requisition
Activity 6: Installation
Activity 7: Inspection and customer acceptance
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities |
OT |
MT |
PT |
Activity 1 |
2 |
3 |
4 |
Activity 2 |
3 |
6 |
9 |
Activity 3 |
4 |
8 |
12 |
Activity 4 |
6 |
8 |
10 |
Activity 5 |
8 |
10 |
12 |
Activity 6 |
10 |
14 |
18 |
Activity 7 |
4 |
6 |
8 |
You must also do the following:
Determine the expected completion time and the variance for each activity
Determine the total project completion time and the critical path for the project
Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
Define project management and the necessary requirements.
Analyze implications of changes in project scheduling.
Evaluate application of project management techniques in terms of the firm''s business operational goals and requirements.
Match the measures to correct answers below
: What is the sensitivity, specificity, positive predictive value, negative predictive value, and accuracy of the test? Please match the measures to their correct
|
What is the fair value of the stock based upon the figures
: The market portfolio return you require is 15%. What is the fair value of the stock based upon the figures?
|
What is the present value of your bond
: The bond you’re holding pays you $45 semi-annually for the next ten years. What is the present value of your bond, which has a maturity value of $1,000?
|
The civil war in the united states
: As you know, the Civil War in the United States pitted the northern states against the southern states.
|
Determine the expected completion time
: Determine the expected completion time and the variance for each activity Determine the total project completion time and the critical path for the project
|
What is firm intrincic value and current stock price
: What is a firm's intrincic value? Its current stock price? Is the stock's "true " long-run value more closely related to its intrincic value or to its current p
|
Probability distribution can be approximated by a smooth
: As with discrete random variables, the probability distribution can be approximated by a smooth curve.
|
Retain customers and build profitable customer relationships
: There are six component: offer superior value, attract customers, satisfy customers, retain customers, and build profitable customer relationships.
|
Conclusion differ between using the t or normal critical
: Comparing the answers to (a) and (b), for what range of values of t statistics would the hypothesis test conclusion differ between using the t or normal
|