Determine the expected activity times

Assignment Help Operation Management
Reference no: EM13983332

Problem 1. Arsenal Electronics is going to construct a new $1.2 billion semiconductor plant and has selected four towns in the Midwest as potential sites. The important location factors and ratings for each town are as follows:

Scores (0 to 100)

Location Factor

Weight

Abbeton

Bayside

Cane Creek

Dunnville

Work ethics

0.18

80

90

70

75

Quality of life

0.16

75

85

95

90

Labor laws/unionization

0.12

90

60

60

70

Infrastructure

0.10

60

50

60

70

Education

0.08

80

90

85

95

Labor skill and education

0.07

75

65

70

80

Cost of living

0.06

70

80

85

75

Taxes

0.05

65

70

55

60

Incentive package

0.05

90

95

70

80

Government regulations

0.03

40

50

65

55

Environmental regulations

0.03

65

60

70

80

Transportation

0.03

90

80

95

80

Space for expansion

0.02

90

95

90

90

Urban proximity

0.02

60

90

70

80

Recommend a site based on these location factors and ratings.

Problem 2. Sawyer Furniture is one of the few remaining domestic manufacturers of wood furniture. In the current competitive environment, cost containment is the key to its continued survival. Demand for furniture follows a seasonal demand pattern with increased sales in the summer and fall months, culminating with peak demand in November.

The cost of production is $16 per unit for regular production, $24 for overtime, and $33 for subcontracting. Hiring and firing costs are $500 per worker. Inventory holding costs are $20 per unit per month. There is no beginning inventory. Ten workers are currently employed. Each worker can produce 50 pieces of furniture per month. Overtime cannot exceed regular production. Given the following demand data, use Excel Solver to design an aggregate production plan for Sawyer Furniture that will meet demand at the lowest possible cost.

Input:

Beg. Wkrs

10

Regular

$16

Hiring

$500

 

 

Units/wkr

50

Overtime

$24

Firing

$500

 

 

Beg. Inv.

0

Subk

$33

Inventory

$20

 

 

Month

Demand

Reg

OT

Subk

Inv

#Wkrs

#Hired

#Fired

 

Jan

500

500

0

0

0

10

0

0

 

Feb

500

500

0

0

0

10

0

0

 

Mar

1000

1,000

0

0

0

20

10

0

 

Apr

1200

1,000

200

0

0

20

0

0

 

May

2000

1,000

1,000

0

0

20

0

0

 

Jun

400

400

0

0

0

8

0

12

 

Jul

400

400

0

0

0

8

0

0

 

Aug

1000

1,000

0

0

0

20

12

0

 

Sep

1000

1,000

0

0

0

20

0

0

 

Oct

1500

1,500

0

0

0

30

10

0

 

Nov

7000

3,500

3,500

0

0

70

40

0

 

Dec

500

500

0

0

0

10

0

60

 

Total

17,000

12,300

4,700

0

0

246

72

72

Problem 3. Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders.

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

 

25

30

56

25

100

40

30

20

Scheduled Receipts

 

 

50

 

 

 

 

 

 

Projected on Hand

30

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

Planned Order Receipts

 

 

 

 

 

 

 

 

 

Planned Order Releases

 

 

 

 

 

 

 

 

 

Release orders in periods 1 through 5 for quantities of 50, 50, 56, 50, and 50 respectively.

Problem 4. Fibrous Incorporated makes products from rough tree fibers. Its product line consists of five items processed through one of five machines. The machines are not identical, and some products are better suited to some machines. Given the following production time in minutes per unit, determine an optimal assignment of product to machine:

 

Machine

Product

A

B

C

D

E

1

17

10

15

16

20

2

12

 9

16

 9

14

3

11

16

14

15

12

4

14

10

10

18

17

5

13

12

 9

15

11

Problem 5. The following probabilistic activity time estimates are for a CPM/PERT network.


Time Estimates (days)

 

Time Estimates (days)

Activity

a

m

b

Activity

a

m

b

1

1

2

 6

 7

1

1.5

2

2

1

3

 5

 8

1

3

5

3

3

5

10

 9

1

1

5

4

3

6

14

10

2

4

9

5

2

4

 9

11

1

2

3

6

2

3

 7

12

1

1

1

2094_figure.png

Determine the following:

a. Expected activity times

b. Earliest start and finish times

c. Latest start and finish times

d. Activity Slack

e. Critical Path

Expected Project duration and standard deviation.

Reference no: EM13983332

Questions Cloud

Find the image location for a converging lens : Find the image location for a converging lens using the thin-lens equation. What is the image location if the object is located at a a distance 100 cm from the lens and the lens has a focal length of 25 cm?
How many pumps are required to finish the job on time : One million Kilograms of water need to be pumped form a lake to a reservoir 85 meters above the lake. If the job is to be completed in 24 hours. What output power (in Hp) is required?
Detrimental effects on process capacity : How does this wok cleaning affect the process capacity? If the process capacity does not change due to the cleaning requirement, explain why and if it does, explain two ways to eliminate any detrimental effects on process capacity during the lunch..
Global capital markets : What factors are holding back the creation of a global capital market?What are the pros and cons of replacing national currencies with regional currencies?
Determine the expected activity times : The following probabilistic activity time estimates are for a CPM/PERT network. Determine the following:  Expected activity times and Earliest start and finish times
Authority to hire a new manager for the firm : Ralph Smith, the owner of a medium-sized business which is operated as a sole proprietorship, gives his Vice-President for Personnel, Wanda Brown, authority to hire a new manager for the firm.
How much farther must car travel to encounter next minimum : If the car is at the position of the third maximum after that at point O when it has traveled a distance of y = 400 m northward, what is the wavelength of the signals?
Characteristic of heterogeneity change : Does the service characteristic of heterogeneity change once a service is placed on the web? Please explain.
Personal statement for msc in business analytics : Personal Statement - This is my personal statement for University College London(UCL) as a postgraduate student.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote