Determine the expected activity times

Assignment Help Project Management
Reference no: EM13798763 , Length: 4000

BUSINESS ADMINISTRATION 3C

Question 1:

Consider the following table and answer the questions that follow

Activity

Description

Predecessor

Optimistic time in days

Most likely time in days

Pessimistic time in days

A

Position recruiting

-

5

8

17

B

System development

-

3

12

15

C

System training

A

4

7

10

D

Equipment training

A

5

8

23

E

Manual system test

B,C

1

1

1

F

Preliminary  system

change over

B,C

1

4

13

G

Computer personnel interface

D,E

3

6

9

H

Equipment
modification

D,E

1

2.5

7

I

Equipment testing

H

1

1

1

1

System     debugging

and installation

F,G

2

2

2

K

Equipment changeover

1,1

5

8

11

1.1 Determine the expected activity times

1.2 Develop an activity on arrow network diagram (AOA)

1.3 Determine the earliest start and finish times; and the latest start and finish time

1.4 Determine the critical path

1.5 Determine the expected project duration

Question 2:

CASE STUDY: Project Charter; Payroll Project.

Authorising the Project

This Charter formally authorizes the Payroll Project to develop and implement a new payroll system for use in Jones Consulting Company's payroll group. A project plan will be developed and submitted to the Project Sponsor for approval. The project plan will include: scope statement; schedule; cost estimate; budget; and provisions for scope, resource, schedule, communications, quality, risk, procurement, and stakeholder management as well as project control. All resources will be assigned by the Project Sponsor, Van Johnson, human Resources Director.

Project Scope:

State the scope of the project, its deliverable and what business needs, problems or opportunities the project addresses - a market demand, business need, legal requirement, social need, customer request or technological advance. The purpose of the Payroll project is to improve the timeliness and accuracy of payroll operations. This project meets Jones Consulting's need for improved efficiencies across all departments by reducing payroll cycle time and minimizing staffing required for payroll operations.

The project deliverables shall include: Payroll system design, all coding, testing and implementation of an integrated system for use with existing IT infrastructure and a user guides. The objectives of the Payroll project are: To reduce payroll cycle time by 30% and reduce payroll staffing by 20%. High level risks for this project include: Ensuring implementation is completed without impacting ongoing payroll operations and ensuring there are no issues with migrating payroll accounts from the legacy system to the new system. Success will be determined by the Project Sponsor once the system is implemented and one full payroll cycle has been completed that meets the objectives with no discrepancies.

The Project Manager

The Project Manager, Bill Smith, is hereby authorized to interface with management as required, negotiate for resources, delegate responsibilities within the framework of the project, and to communicate with all contractors and management, as required, to ensure successful and timely completion of the project. The Project Manager is responsible for developing the project plan, monitoring the schedule, cost, and scope of the project during implementation, and maintaining control over the project by measuring performance and taking corrective action.

Milestones

The project plan will be submitted and approved in accordance with the milestone schedule below. Upon approval of the project plan resources will be assigned to the project and work will commence within 5 business days. The Project Sponsor must approve any schedule changes which may impact milestones. A detailed schedule will be included in the project plan. The high level milestone schedule is:

Feb 1, 2015 - Project Plan Complete and Approved
Mar 31, 2015 - Payroll Design Completed
May 31, 2015 - Coding Completed
June 30, 2015 - Testing Completed
July 31, 2015 - Beta Testing Completed
Sept 30, 2015 - Implementation Completed
Oct 15, 2015 - One Payroll Cycle Complete and Project Completion

Paragraph 5: Project Budget

The budget for the Payroll project is R420,000. It is to be funded through the FYxx Human Resources Technology Budget.

SPONSOR ACCEPTANCE

Approved by the Project Sponsor:
Date:
Project Sponsor Name
Project Sponsor Title

Use the following checklist to compile a project scope statement.

From the Project charter above create a detailed scope statement. Use the following scope checklist:

1. Objectives
2. Deliverables
3. Milestones
4. Technical requirements
5. Limits and exclusions

Question 3:

3.1 Formulate at least five risks and associated impacts based on your scope statement developed in question 2 above.

3.2 With motivation, score the risks on a quantitative risk assessment template.

3.3 Create a risk management plan for all the formulated risks

Reference no: EM13798763

Questions Cloud

Important physical characteristics of region : What are the important physical characteristics of your region and what is the impact on the region because of this?
Problems based on voip traffic engineering : What access link bandwidth (Kbps from the online calculator) is required to connect the company's location to the Internet?
Healthcare between three countries us being one : Give reasons why this issue is a problem in the first place.  Describe 5 distinct instances where this world issue has caused a problem within the context of local and international business.
Determine the components of a well-defined communications : Imagine that your company has purchased new software to reduce time in calculating customers' accounts. Determine the components of a well-defined communications plan that may be used to minimize this risk of implementing the new software.
Determine the expected activity times : Determine the expected activity times - Develop an activity on arrow network diagram (AOA)
Stresses in a rock result in the various folds and faults : Rock structures (folds and faults) are created by the stresses that deform the rocks. Write a one-page explanation of how the various stresses in a rock result in the various folds and faults.
Global warming- cause and mitigation : Global Warming: Cause and Mitigation. Compare and contrast natural versus anthropogenic climate changes. Include specific examples of each
Creating a continuous supply : Background - Even though water is continually recycled from the ocean into the atmosphere and back to Earth, creating a continuous supply, we often speak of water shortages, especially groundwater shortages.
Obtain magnitude of the average force acting on the ball : A 583 g ball strikes a wall at 14.5 m/s and rebounds at 11.6 m/s. The ball is in contact with the wall for 0.047 s. What is the magnitude of the average force acting on the ball during the collision

Reviews

Write a Review

Project Management Questions & Answers

  Benefits and disadvantages offered by each type of contract

Evaluate procurement contract types that are available to facilitate external goods and services. Describe the benefits and disadvantages offered by each type of contract. Determine which type of contract provides greater risk to buyer

  Construct the pert network diagram

Construct the PERT Network Diagram - state the Critical Path of the project

  Public activity in the u.s. economy

Provide the reasons why this activity is a major part of the public activity in the U.S. economy.

  How does quality and the team process of storming work

How does quality and the team process of storming work together and give examples.

  Locating the position of hubthe following table gives the

locating the position of hubthe following table gives the map coordinates and the shipping loads for a set for a set of

  Project management-budget vs actual costs

Explain what might a seasoned project manager who understands earned value recognize as not-good-news about the situation and its impact on the project

  Project management techniques for big data management

Write a report of 2500 words on one of the listed Statements - Topics. The report should demonstrate that the team has thoroughly researched the keywords and the key issues of their selected statement/topic including any existing arguments.

  Question based onintercultural communication

Intercultural Communication: Interpreting Phrases In Different Languages - explain how can someone in a non-dominant culture interpret the squeaky wheel gets the grease

  Project management amp wbs1 why are accurate estimates

project management amp wbs1. why are accurate estimates critical to effective project management? please explain in

  Objectives of business plan

Describe the preferred timing and objectives of your business plan. Include an Excel spreadsheet with critical decisions and dates

  Project-s mirr if reinvestment rate opportunity is given

If Project A's IRR is 61.8% and the reinvestment rate opportunity is 10%, what is the project's MIRR?

  Choose a project that you would like to do it can be either

choose a project that you would like to do. it can be either personal or work related. how would you go about creating

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd