Determine the critical path and the expected completion

Assignment Help Operation Management
Reference no: EM131258489 , Length: 2

QUESTION 1

The following information is available for a large fundraising project.

 

Activity

Activity Time (days)

Activity Cost ($)

Immediate Predecessor(s)

A

3

100

--

B

4

150

--

C

2

125

A

D

5

175

B

E

3

150

B

F

4

200

C, D

G

6

75

C

H

2

50

C, D, E

I

1

100

E

J

4

75

D, E

K

3

150

F, G

L

3

150

G, H, I

M

2

100

I, J

N

4

175

K, M

O

1

200

H, M

P

5

150

N, L, 0

a) Determine the critical path and the expected completion time of the project.

b) Plot the total project cost, starting from Day1 to the expected completion date of the project, assuming the earliest start times for each activity. Compare the result to a similar plot for the latest start times. What implication does the time differential have for cash flows and project scheduling?

QUESTION 2

You are the project manager of a software installation project. You would like to find the minimum-cost schedule for your project. There is a $1000-per-week penalty for each week the project is delayed beyond 25 weeks. In addition, your project team determined that indirect costs are $2,500 per week.

 

Activity

Immediate Predecessor

Normal Time (weeks)

Normal Cost ($)

Crash Time (weeks)

Crash Cost ($)

A

--

5

2,000

3

4,000

B

--

8

5,000

7

8,000

C

A

10

10,000

8

12,000

D

A, B

4

3,000

3

7,000

E

B

3

4,000

2

5,000

F

D

9

8,000

6

14,000

G

E, F

2

2,000

2

2,000

H

G

8

6,000

5

9,000

I

C, F

9

7,000

7

15,000

a) What is the target completion week?

b) How much would you save in total project costs with your schedule?

QUESTION 3:

Recently, you were assigned to manage a project to remodel the seminar room for you company. You are provided with the precedence relationships. In addition, you have asked your team to estimate the amount of time that they expect each of the activities to take. Their responses are shown in the following table:

 

Activity

 

Optimistic

 

Most Likely

 

Pessimistic

Immediate Predecessor

A

5

8

11

--

B

4

8

11

--

C

5

6

7

A

D

2

4

6

A

E

4

7

10

B, D

a) Construct the network diagram

b) What is the expected completion time of the project?

c) What is the probability of completing the project in 21 days?

d) What is the probability of competing the project in 17 days?

Reference no: EM131258489

Questions Cloud

Create a program for an automatic teller machine : Write a program for an automatic teller machine that dispenses money. The user should enter the amount desired (a multiple of 10 dollars) and the machine dispenses this amount using the least number of bills.
Determine the arbitrary integration constant : Determine the arbitrary integration constant in a) via the boundary condition in x = 0.
Draw a new graph containing same information : 1. (Continuation from Question 1 - please answer using the same graph as in Q1, or draw a new graph containing same information as your Q1 graph). Let B from Q1 part b represent the long run full-employment equilibrium for the money market.
How long should a typical agent be expected : He takes an average of 50 seconds per passenger and is rated 110% in performance. - How long should a typical agent be expected to take to make seat assignments?
Determine the critical path and the expected completion : What is the target completion week - How much would you save in total project costs with your schedule and Construct the network diagram
Create both these versions of your design in adobe animate : Using your multi-page presentation, create both these versions of your design in Adobe Animate. The point of this task is to present the same content to users in two different formats, and to evaluate which form of interaction they prefer.
Find the standard time for this blood test : The hospital has a personal, fatigue, and delay allowance of 16%. - Find the normal time for this process. - Find the standard time for this blood test.
Determine the von mises stress at point d in cross-section : Find the distribution of the internal forces and the moment Mz and shear force Qz at the section indicated by the dashed line immediately to the left of the force P.
Define the organizational architecture in apple inc : Define the Organizational Architecture in Apple Inc. Explain in detail the corporate governance in Apple Inc.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd