Part A-
1. A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.
![1869_img1.png](https://secure.expertsmind.com/CMSImages/1869_img1.png)
Activity |
Precedence Activities |
Activity Time (weeks) |
ES |
LS |
EF |
LF |
Slack |
Critical Path? |
A |
|
|
|
|
|
|
|
|
B |
|
|
|
|
|
|
|
|
C |
|
|
|
|
|
|
|
|
D |
|
|
|
|
|
|
|
|
E |
|
|
|
|
|
|
|
|
F |
|
|
|
|
|
|
|
|
G |
|
|
|
|
|
|
|
|
H |
|
|
|
|
|
|
|
|
I |
|
|
|
|
|
|
|
|
Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%?
2. Given this network with activities and times estimated in days,
![2138_img2.png](https://secure.expertsmind.com/CMSImages/2138_img2.png)
Activity |
Optimistic |
Most Probable |
Pessimistic |
A |
2 |
5 |
6 |
B |
1 |
3 |
7 |
C |
6 |
7 |
10 |
D |
5 |
12 |
14 |
E |
3 |
4 |
5 |
F |
8 |
9 |
12 |
G |
4 |
6 |
8 |
H |
3 |
6 |
8 |
I |
5 |
7 |
12 |
J |
12 |
13 |
14 |
K |
1 |
3 |
4 |
a. What are the critical path activities?
b. What is the expected time to complete the project?
c. What is the probability the project will take more than 28 days to complete?
Part B-
1. Greenfields is a mail order seed and plant business. The size of orders is uniformly distributed over the interval from $25 to $80. Use the following random numbers to generate the size of 10 orders.
41 .99 .07 .05 .38 .77 .19 .12 .58 .60
2. An airline reservation system first asks customers whether they want to schedule a domestic or an international flight. Sixty-five percent of the reservations are for domestic flights. The time distribution of advance sales is also important, and it is given below.
![743_img3.png](https://secure.expertsmind.com/CMSImages/743_img3.png)
a. Place the appropriate random number ranges in the tables above.
b. Set up and perform a simulation for three customers. Determine whether they want a domestic or international flight, and how far in advance the reservation is being made. Use random numbers from this list:
.632 .715 .998 .671 .744 .021
Describe development and influence of cubism on twentieth
: Discuss Manet's relationship with historical painting. What examples did he follow, and in what ways did he radically break from those examples?
|
Government contracting-regarding terminations
: You are a small business that has done some Government contracting so you know about FAR Part 49 regarding terminations. You have been approached by a large business to be a subcontractor to them on a new program. You are ecstatic! The subcontract do..
|
Health policy and health reform
: This week you are reading about health policy and health reform. After reading this material, do you believe that the government (at any level) should play a larger role in driving the direction of the U.S. health care system or do you believe..
|
Advantages and disadvantages of the electoral college
: Discuss the advantages and disadvantages of the Electoral College
|
Determine the critical path
: A project network is shown below. Use a forward and a backward pass to determine the critical path
|
Identifying and analyzing the role of stakeholders
: In this assignment students will gain expertise in identifying and analyzing the role of stakeholders in the U.S. Health Care Sector, examining the health care sector from the perspective of stakeholders, and examining the leadership and managemen..
|
Compute the predetermined overhead rate for each department
: Compute the predetermined overhead rate for each department. What is the total cost of the furniture prouced for City Furniture?
|
Sketch and label the corresponding circuit
: Show how to implement this expression if only gates with at most 4 inputs can be used. Rewrite the expression for c8 using parentheses to show the associated grouping of inputs. Sketch and label the corresponding circuit and determine its cost. The ..
|
How does multitasking work
: How does multitasking work? How does multitasking confuse the resource availability of project team personnel?
|