Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Consider the following table and answer the questions that follow
Activity
Description
Predecessor
Optimistic time in days
Most likely time In days
Pessimistic time in days
A
Position recruiting
5
8
17
System development
3
12
15
C
System training
4
7
10
D
Equipment training
23
Manual system test
B,C
1
F
Preliminary system change over
13
G
Computer personnel Interface
0,E
6
9
H
Equipment modification
D,E
2.5
Equipment testing
System debugging
and Installation
F,G
2
Equipment changeover
1,1
11
1.1 Determine the expected activity times
1.2 Develop an activity on arrow network diagram (ADA)
1.3 Determine the earliest start and finish times; and the latest start and finish time
1.4 Determine the critical path
1.5 Determine the expected project duration
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd