Determine the cost per unit for jobs at the end of august

Assignment Help Managerial Accounting
Reference no: EM133178988

Question - Job Costs - At the end of August, Rothchild Company had completed Jobs 40 and 42. Job 40 is for 10,000 units, and Job 42 is for 11,000 units.

The following data relate to these two jobs:

On August 4, Rothchild Company purchased on account 12,000 units of raw materials at $14 per unit. On August 24, raw materials were requisitioned for production as follows: 5,000 units for Job 40 at $8 per unit and 6,200 units for Job 42 at $14 per unit.

During August, Rothchild Company accumulated 3,500 hours of direct labor costs on Job 40 and 4,200 hours on Job 42. The total direct labor was incurred at a rate of $25.00 per direct labor hour for Job 40 and $23.50 per direct labor hour for Job 42.

Rothchild Company estimates that total factory overhead costs will be $810,000 for the year. Direct labor hours are estimated to be 90,000.

Required -

a. Determine the balance on the job cost sheets for Jobs 40 and 42 at the end of August.

b. Determine the cost per unit for Jobs 40 and 42 at the end of August.

Reference no: EM133178988

Questions Cloud

Evaluate contemporary hr and employment-related issues : Evaluate contemporary HR and employment-related issues in terms of their impact on employees.
Evaluate contemporary hr and employment-related issues : Evaluate contemporary HR and employment-related issues in terms of their impact on employees.
Describe proposal for onboarding new employees : As the newly hired HR Manager with XYZ Company, you are responsible for developing a page of talking points with your President and CEO.
Determine total costs to consider in computing percentage : Le Mirage Construction reported the costs on the first year it was contracted to put up a mall: Determine total costs to consider in computing percentage
Determine the cost per unit for jobs at the end of august : Rothchild Company estimates that total factory overhead costs will be $810,000 for the year. Determine the cost per unit for Jobs at the end of August
Difference between a master budget and an operating budget : What is the major difference between a master budget and an operating budget? Compare the benefits and risks of creating and using these two budgets
Describe three ways of communicating nonverbally : Describe three ways of communicating nonverbally and explain how this communication is harmful or helpful in your relationship with human services consumers.
Competency-based system : Do you choose a results- or competency-based system? Defend your response.
Compute the variable overhead spending variance : Included in the $30.00 is $13.20 for direct materials (3 yards) and $12.00 of direct labor (2 hours). Compute the variable overhead spending variance

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd