Question - RT Enterprise bought a machine on 1 January 20X4 for $1,000,000. The following expenditure is incurred;
Installation costs of $100,000.
Cost of storage for the machine of $50,000 as it was delivered before the factory floor is ready for installation.
Insurance of $150,000 were incurred as the management seek to reduce the risk of fire.
Expenses incurred to test the functionality of the installation.
Pre-production tests were carried out incurring $180,000. Meanwhile a revenue of $20,000 earned by RT Enterprise from the pre-production testing.
Cost incurred to launch the product manufactured by the machine amounting to $50,000.
Maintenance contract for the machine sign-up for the next three years amounting to $100,000.
The machine incurs a transportation cost of $80,000 to bring it to the factory.
Staff training costs to handle the machine amounted to $120,000.
Required - Determine the cost capitalized for the machine.