Question 1: A manufacturer of wood screws periodically examines screws heads for the presence or absence of burrs. Subgroups of 300 screws are selected and examined using a carefully designed procedure. The collected data is as follows:

Observation

Number of Screws with Burrs

1

19

2

16

3

11

4

6

5

22

6

2

7

4

8

7

9

5

10

27

11

7

12

13

13

17

14

29

15

1

16

2

17

19

18

28

19

24

20

23

a- Find the centerline (show your calculations)

b- Find the control limits (show your calculations)

c- Use MINITAB to develop the appropriate control chart

d- Are there any special causes of variation? Which observations?

e- What to do next?

Question 2: A given model of large radar dish represents the area of opportunity in which nonconformities may occur. Results of quality check for 25 radar assemblies are as follows:

Radar Assembly Number

Number of Nonconformities

1

25

2

60

3

28

4

65

5

91

6

56

7

40

8

54

9

90

10

44

11

62

12

81

13

70

14

75

15

24

16

50

17

70

18

56

19

21

20

88

21

34

22

82

23

53

24

102

25

64

a- Determine the centerline (show your calculations)

b- Determine the control limits (show your calculations)

c- Use MINITAB to develop the appropriate control chart

d- Are there any indications of lack of control?

e- What to do next?

Question 3: Workers at a packaging operation shovels a granular product from a large pile into sacks that are then sealed and placed on pallets for shipping. A sequence of 25 subgroups each consisting of the weights of 5 sacks has been recorded as follows:

 

Observations

Subgroup #

Sack 1

Sack 2

Sack 3

Sack 4

Sack 5

1

35.4

35.6

34.8

34.7

34.8

2

36

35.6

34.9

34.8

35.9

3

35.2

35

35

35.4

35.1

4

34.8

35.8

35.2

35

34.9

5

34.2

35

36.1

34.9

35.1

6

36

35

35.2

34.8

34.9

7

36.1

34.9

34.5

35

35.1

8

35.1

35

35.6

34.9

36.2

9

35

35.6

36.1

34.8

35.6

10

35.4

35.8

36

34.2

36

11

35.2

35.3

35.2

35.9

34.8

12

35.9

36

35.1

35.1

35.6

13

35.2

35.6

35

34.9

35

14

35.2

35.6

35.8

35

35.1

15

34.9

34.8

35

35.2

34.9

16

35.2

35.3

35.2

35.6

35.1

17

35.6

35.8

35.2

35.4

34.9

18

35.2

35.6

35.4

35.6

35.2

19

34.7

34.9

35.6

35.2

35

20

35

35.1

35.6

35

35.1

21

35.6

35

35.8

35.2

34.6

22

34.9

35.1

35.6

35

35.2

23

35.9

36

35.2

36

35.2

24

35.2

35.1

35.4

34.9

35.1

25

35.2

35.2

35.1

35.6

34.9

a- What is the appropriate control chart that can be used by the quality engineer in this case?

b- Determine the control limits (show your calculations)

c- Construct the appropriate control chart for the data above using MINITAB.

d- Is the process in-control? If not, when does the out-of-control behavior occur?

e- If the process is found to be out of control, drop the out-of-control points and use MINITAB to re-construct the control chart.

f-  Is the process now in-control? If not, what to do next?

Question 4: Viscosity is one of the important quality characteristics of paste ink used in printing presses.  A viscosity measure is taken at the end of production of each batch of ink. Viscosity measures for 50 consecutive batches have been recorded as follows:

Sample

Viscosity

 

 

Sample

Viscosity

1

305

 

 

26

291

2

274

 

 

27

301

3

290

 

 

28

290

4

314

 

 

29

290

5

291

 

 

30

308

6

315

 

 

31

306

7

301

 

 

32

292

8

298

 

 

33

279

9

306

 

 

34

276

10

305

 

 

35

285

11

270

 

 

36

296

12

296

 

 

37

275

13

307

 

 

38

299

14

284

 

 

39

301

15

280

 

 

40

294

16

264

 

 

41

312

17

299

 

 

42

289

18

270

 

 

43

278

19

275

 

 

44

288

20

276

 

 

45

299

21

294

 

 

46

270

22

313

 

 

47

308

23

304

 

 

48

298

24

310

 

 

49

294

25

271

 

 

50

306

a- What is the appropriate control chart that can be used by the quality engineer in this case?

b- Determine the control limits (show your calculations)

c- Construct the appropriate control chart for the data above using MINITAB.

d- Is the process in-control? If not, when does the out-of-control behavior occur?

e- If the process is found to be out of control, drop the out-of-control points and use MINITAB to re-construct the control chart.

f-  Is the process now in-control? If not, what to do next?

Reference no: EM13537593

Questions Cloud

Estimate how much time does the lift take : Your sofa won't fit through the door of your new sixth-floor apartment, so you use a 1.08kW motor to lift the 84.4kg sofa 15.6m from the street. How much time does the lift take
Find the centerline and find the control limits : Find the centerline and find the control limits, Use MINITAB to develop the appropriate control chart and Are there any special causes of variation?
Explain molar concentration of commercial hydrochloric acid : Calculate the molar concentration of commercial hydrochloric acid, if the solution contains 37% for mass in HCl, and if the solution has a density of 1.18 g/mL.
Explain the solution contains exactly 1 kg of solvent : A solute with MW = 67.1 g/mol is prepared in an aqueous solution in which the molality is 3.08 m. The solution density is 1.0616 g/cm^3. To simplify the following calculations, assume that the solution contains exactly 1 kg of solvent.
Determine the control limits : What is the appropriate control chart that can be used by the quality engineer and determine the control limits
Calculate what is the force of friction : Indiana Jones is pushing back a 305 kg box of treasure which slides 4.6 m down a 25° incline and kept from accelerating. What's the Force of Friction
What rms voltage does the second generator produce : A capacitor is connected to an ac generator that has a frequency of 3.4 kHz and produces a rms voltage of 1.9 V. What rms voltage does the second generator produce
How to calculate the molar concentration of hcl : Calculate the molar concentration of HCl if 25 mL of the HCl solution quantitatively react with 19.58 mL of an 0.1062 M solution of NaOH. Write the balanced equation.
Equity of a system : Majority of the people from ever question in equity of a system where most of people drudge along, paying series of heavy taxes for which they get nothing in return.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd