Determine the amount of value-added ratio

Assignment Help Managerial Accounting
Reference no: EM132767770

Problem - Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 45 printed circuit boards. Each board requires 5 minutes of board assembly time. After each batch is completed, the operator moves the assembled boards to the final assembly area. This move takes 10 minutes to complete.

The final assembly for each stereo unit requires 15 minutes and is also done in batches of 45 units. A batch of 45 stereos is moved into the test building, which is across the street. The move takes 20 minutes. Before conducting the test, the test equipment must be set up for the particular stereo model. The test setup requires 25 minutes. The units wait while the setup is performed. In the final test, the 45-unit batch is tested one at a time. Each test requires 9 minutes. The completed batch, after all testing, is sent to shipping for packaging and final shipment to customers. A complete batch of 45 units is sent from testing to shipping. The Shipping Department is located next to testing. Thus, there is no move time between these two operations. Packaging and labeling requires 10 minutes per unit.

Required -

1. Determine the amount of value-added and non-value-added lead time and the value-added ratio in this process for an average stereo unit in a batch of 45 units. Round percentages to one decimal place. Categorize the non-value-added time into wait and move time.

2. How could this process be improved so as to reduce the amount of waste?

Reference no: EM132767770

Questions Cloud

What time does Simmons arrive home : Before leaving the doctor's office, Simmons waited 10 minutes at the business office to pay for the office visit. What time does Simmons arrive home
Organizations to have disaster recovery plan : Why is important for organizations to have a disaster recovery plan?
Analysis of types and patterns of innovation : Using the company that you wrote about in week one or another company of interest, identify at least two different technological innovations
Define change models and degree of infrastructure change : Based on your understanding of the models of the change process in your Organizational Change: An Action-Oriented Toolkit text and figure 3.1 in Mastering.
Determine the amount of value-added ratio : Determine the amount of value-added and non-value-added lead time and the value-added ratio in this process for an average stereo unit in a batch of 45 units
Hackers launch cyber attacks that affect several parts : In this scenario, hackers launch cyber attacks that affect several parts of the nation's financial infrastructure over the course of several weeks.
What is additional cost per pound of central glass company : Considering only inventory financing costs, what is the additional cost per pound of Central Glass Company's bid if the annual cost of money is 8%
Disaster recovery process : What sacrifices would a business have to make if the disaster recovery process were turned over to a government agency?
Explain the listening types and stages of listening : Explain the listening types (informational, critical, and empathic) and stages of listening. Discuss the key differences between hearing and listening.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd