The Geely car company makes three types of cars small, midsize and SUV. There has been some issue with determining a production schedule that is more in line with customer needs. Management has it that making more SUV's will improve the company's profitability and they are asking you to take a look in to this. A consultant has suggested that it would make more sense for them to use the ABC accounting method to determine their production plan. See the tables below and answer all the questions that follow. Also conclude by suggesting which method would be in their best interests.

Table 1

Product

Raw Material Cost
($/Unit)

Price
($/Unit)

Minimum Demand
(Units per Month)

Maximum Demand
(Units per Month)

Small Car

$10,000.00

$20,000.00

500

900

Mid Size Car

$12,000.00

$35,000.00

350

500

SUV

$15,000.00

$45,000.00

290

500

Table 2

Product

Motor Assembly
(Minimum Time Per Unit in minutes)

Final Assembly
(Minimum Time Per Unit in minutes)

Test
(Minimum Time Per Unit in minutes)

Minimum Amount of time for assembly (in minutes)

Small Car

3

2

1

3

Mid Size Car

4

3

4

5

SUV

5

6

5

7

 Table 3

Hours Per Month in one 8 hour shift for 250 Workers

60000

hrs

Hourly Labor Costs per worker

$25.00

 

Overhead Costs

$20,000,000.00

 

Number of Workers

250

Workers

1. The new production schedule, due to the recession, calls for 859 small car, 375 mid-size car and 280 SUV's to be made.  (See first worksheet in excel to provide all your answers to this question). Using the Traditional method of accounting: 

a. Determine the amount of time it takes to make each product in the production plan?
b. Determine the material costs for this production plan?
c. Determine the Labor costs for this production plan?
d. Determine the Overhead costs for this production plan?
e. Determine the revenue that is generated from this production plan?
f. Determine the profit per product with this production plan?
g. Determine the profit per unit based on the traditional cost allocation method?
h. Determine the Total Profit of the Company based on this production plan?

Table 4.

 

Category

Plant and Equipment

Management

Purchasing

Sales and Shipping

Total Cost

$    7,000,000.00

$           5,000,000.00

$4,500,000.00

$3,500,000.00

Cost Allocation

Square feet

Labor hours

Purchase orders

Customer orders

Total units used

1200000

650000

95573

5030

Small Car

200000

50000

5320

280

Mid Size Car

400000

300000

28500

1500

SUV

600000

300000

61753

3250

Note: The production plan stays the same for both cost allocation methods 2. Using the same production and now the ABC method do the following (See first worksheet in excel to provide all your answers to this question)

a. Determine how overhead cost is allocated for each product base on the department of origin?
b. Determine the profit per product with this production plan?
c. Determine the Profit per unit based on the Activity Based Cost Allocation Method?
d. Determine the Total Profit of the Company based on this production plan?

Question # 2

The table below represents the process taken for the making of an Integrated circuit. You have been hired to review the operations of this facility and also to determine if this facility is performing at its best.

Process

Rate (p/hr)

Time (hr)

Lamination

125.7

8.6

Machining

143.6

5.7

Internal Circuitize

230.3

9.2

Optical Test/Repair - Int

150.5

3

Lamination – Composites

180.8

2.4

External Circuitize

159.9

3.2

Optical Test/Repair - Ext

150.5

1

Drilling

185.9

10.2

Copper Plate

136.4

7.8

Procoat

143.9

9.5

Sizing

126.5

10.2

EOL Test

169.5

2.5

a. How long does it take for a product to go through the entire production line?
b. What is the critical amount of WIP (w0) needed by this facility?
3. If the facility has an average cycle time of 250hrs and an average WIP of 23000 chips what is the average throughput of the line?
4. What is the Practical Worst Case cycle time of this line? Is this line doing well?
5. What is the takt time of the line given that 900 chips have to be made over the course of 890 hrs?
6. Can the production line make this takt time?
7. How many machines will be needed at each station? 

Reference no: EM13968696

Questions Cloud

Demand at each vendor and total demand for the system : The boardwalk on the Paradise City Beach is 4 miles long with mile markers at 0, 1, 2, 3, and 4 miles. There are 100 customers at each mile marker and each customer's demand for ice cream is given by the function: D = 24 - 4d, where d = distance betw..
Using technologies to facilitate virtual meetings : All the following are the advantages of using technologies to facilitate virtual meetings, EXCEPT:?
An important cause of ineffective or useless meetings : An important cause of ineffective or useless meetings is:?
Best strategy for conflict : When all parties seriously want a win-win solution and have enough time, _____ is the best strategy for conflict resolution.
Determine the amount of time it takes to make each product : Determine the amount of time it takes to make each product in the production plan. Determine the material costs for this production plan. Determine the Labor costs for this production plan. Determine the Overhead costs for this production plan. Deter..
Integrationist view of managing conflict : Which of the following statements relates to the integrationist view of managing conflict?
About the batna : Which of the following is true about BATNA?
About integrative bargaining : Which of the following statements about integrative bargaining is true?
New product development stages for convenience goods : In regards to Marketing, Because of expenses, the new product development stages for convenience goods should be reduced to idea generation, screening, and then, product development and commercialization (national roil-out).

Reviews

Write a Review

Operation Management Questions & Answers

  Illustrate what are some of problems aecs facing

Illustrate what are some of problems AECS facing. Are they inherent in its model or they could be rectified while keeping model intact.

  Implementing logistics measurement system

Discuss some of the key considerations for a logistics manager who is designing and implementing a logistics measurement system in his or her organization.

  Servant leader instil spirit of consciousness-gratitude

How and why should a servant leader instil a spirit of consciousness, gratitude, and forgiveness in their organization?

  Understanding of management and organizational behavior

How does an understanding of management and organizational behavior lead to organizational effectiveness and efficiency?

  Discuss why security isn ot just a technology issue

Discuss why Security isn't just a technology issue? Why does the business unit need to be involved?

  Estimate the durations of the activities

Based on your knowledge of your anticipated resources you will have to do the work of the activities, estimate the durations of the activities. You may use Microsoft Project now, or defer use of Microsoft Project to the Phase 4 IP.

  Hire employees who will positively contribute

As the general manager of a large contracting firm, it is your responsibility to hire employees who will positively contribute to the organization. Recently, your project manager of the past 20 years, who has been both reputable and trustworthy, r..

  Sentences to avoid dangling and misplaced modifiers

Revise the following sentences to avoid dangling and misplaced modifiers.

  Represent major opportunities or threats

Identify five key economic variables that could represent major opportunities or threats to a bank in your town or city. Identify which that you believe to be most important, and describe at least one strategic response.

  Information communicated upward

It has often been claimed that the greatest barrier to getting essential information communicated upward from the work force is management's failure to act on previous information. Why might this be so?

  Interger programming please see attached file which related

please see attached file which related to linear programming and answer part a b in full details with posting pom-qm

  Pert/cpm techniques

Discuss the use of PERT/CPM techniques for managing projects. Describe what PERT/CPM does. Discuss advantages and disadvantages of using it.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd