Question - This exercise parallels the machine-purchase decision for the Mendoza Company that is discussed in the body of the chapter. Assume that Mendoza is exploring whether to enter a complementary line of business. The existing business line generates annual cash revenues of approximately $4,950,000 and cash expenses of $3,735,000, one-third of which are labor costs. The current level of investment in this existing division is $12,600,000. (Sales and costs of this division are not affected by the investment decision regarding the complementary line.)

Mendoza estimates that incremental (noncash) net working capital of $40,000 will be needed to support the new business line. No additional facilities-level costs would be needed to support the new line-there is currently sufficient excess capacity. However, the new line would require additional cash expenses (overhead costs) of $450,000 per year. Raw materials costs associated with the new line are expected to be $1,480,000 per year, while the total labor cost is expected to double.

The CFO of the company estimates that new machinery costing $4,100,000 would need to be purchased. This machinery has a four-year useful life and an estimated salvage (terminal) value of $656,000. For tax purposes, assume that the Mendoza Company would use the straight-line method (with estimated salvage value considered in the calculation).

Assume, further, that the weighted-average cost of capital (WACC) for Mendoza is 15% (after-tax) and that the combined (federal and state) income tax rate is 28%. Finally, assume that the new business line is expected to generate annual cash revenue of $4,275,000.

Required - Determine relevant cash flows (after-tax) at each of the following three points: (1) project initiation, (2) project operation, and (3) project disposal (termination). For purposes of this last calculation, you can assume that the asset is sold at the end of its useful life for the salvage value used to establish the annual straight-line depreciation deductions; further, you can assume that at the end of the project's life Mendoza will fully recover its initial investment in net working capital.

Reference no: EM132867331

Questions Cloud

Describe the possible impact on collection : Describe the possible impact on collection if insufficient information is given as required in the collection instruction as per URC522.
Internal and external stakeholder analysis : Analyse and synthesise the fundamentals of business in the contemporary environment and Construct and Justify a professional value proposition as a business
Characteristics of an organizational decision support system : What are the four main characteristics of an Organizational decision support system
EDGI900 Introduction to Technology in Education Assignment : EDGI900 Introduction to Technology in Education Assignment Help and Solution, University of Wollongong - Assessment Writing Service
Determine relevant cash flows : Determine relevant cash flows (after-tax) at each of the following three points: (1) project initiation, (2) project operation, and (3) project disposal
Identify staffing qualifications listed in education : Identify the staffing qualifications listed in the Education and Care Regulations*that are required to assist in the management of children with anaphylaxis
What amount of depreciation will Laguna Madre record : What amount of depreciation will Laguna Madre record in its income statement on December 31 of the current? year
What surprised you with the ted talk : Ted Talk by Erez Yoeli "How to motivate people to do good to others"
Why is country migration data generally imperfect : What are the problems in utilizing some general distinction categories (e.g. gender, race, ethnicity, age, sexual orientation, and disability) to define diversi

Reviews

Write a Review

Cost Accounting Questions & Answers

  What is the amount of a gain or loss on realization

What is the amount of a gain or loss on realization and how should the gain or loss be divided between Lyle and Fisher?

  What will be the company operating profit

If LSB's sales increase by $20,000, what will be the company's operating profit? Contribution Margin 60,000. Variable Costs 40,000

  Determine the proposals internal rate of return

Determine the proposals internal rate of return, Using a discountrate of 10 percent, determine the net present value of the investment proposal

  What is the cost function of the operation cost

What is the cost function of the Operation cost? Using the high-low points method, the variable cost of operations per kilo of materials used is

  The data below relate to a product of colfax

the data below relate to a product of colfax company.standard costs material 2 pounds at 6 per pound 12 per unitlabor

  Calculate usage and mix variances

Calculate material cost, price, and usage and mix variances. During a particular period, 100 tons of mixture X was produced 35 tons of material A

  In 2009 jed james began planting a vineyard the cost of the

in 2009 jed james began planting a vineyard. the cost of the land preparation labor rootstock and planting were

  During 2013 jeff smallwood worked for two different

during 2013 jeff smallwood worked for two different employers. until may he worked for rowland constructions company in

  How do calculate the economic order quantity

Calculate the economic order quantity. Wilson Company is trying to figure out the most efficient inventory management, Annual sales units required 10,000

  Analyse principles and trends in performance

Performance Management and Control - Identify and critically analyse principles and trends in Performance Measurement and Control and Determine the different budgeting techniques and critically evaluate their use in short term decision making

  Determine what is the break-even point in units

Top Sail Company produces one type of machine with the following costs and revenues for year. Total Revenues: 5,600,000 What is the selling price per unit What is the variable cost per unit What is the contribution margin What is the break-even point..

  What is the annual inventory carrying cost

The quarterly demand for the material is 10,000 units. The order cost is 200 per order. What is the annual inventory carrying cost

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd