Rain delays in pouring concrete. A contractor is planning to pour concrete on Monday morning, but he has heard a weather forecast that rain is expected. The probabilities of rain are 0.8 on Monday, 0.6 on Tuesday, 0.3 on Wednesday, and 0.1 on Thursday and each succeeding day for five days.
If it rains on the day that concrete is poured, there will be an immediate $10,000 damage cost and a delay of five days in the construction schedule. For every day of delay, $4000 is lost. The delay cost applies even if it is the contractor who decides to delay the pour.
Determine on which day the concrete should be poured. What is the associated expected cost?
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd